The anticipated work schedule for VT 116:

Written by on July 26, 2018 in Middlebury-Starksboro VT 116

For the week beginning Monday, July 30, 2018:

Monday thru Friday:

  • Cold planning the side road approaches and various approaches on the main line between E. Middlebury and Bristol
  • Miscellaneous clean up work throughout the project.

We are awaiting notification on the culvert work that was postponed.   I will post it if this gets scheduled for next week.

The anticipated work schedule for the I-91 Rockingham Bridges:

Written by on July 26, 2018 in Rockingham Bridges-I91
The anticipated work schedule for the I-91 Rockingham Bridges:

NB concrete beams in place

For the week beginning Monday, July 30, 2018:

I-91 northbound bridge activities:

Monday thru Friday:

  • Continued preparation work on the set girders to include concrete closure pours.

 

VT 117 – July 26, 2018

The anticipated work schedule is as follows:

  • Continued shoulder cleanup work within the VT 289 area.
  • Continued underdrain work will continue just east of Barber Farm Road, Jericho.
  • Begin reclaiming the roadway from the Essex/Jericho Town line proceeding westbound. Reclaim takes 10″ of the road surface and basically rototills it and places it back as a gravel surface, recycling the existing material.
Continued roadway maintenance as needed.
 
SLOW DOWN FOR ROUGH ROAD CONDITIONS!
EXPECT DELAYS DURING PEAK HOURS!

VT 116 – July 25, 2018

The anticipated work schedule is as follows:
• Continued shoulder cleanup work from the VT 289 on ramp to Sand Hill Road.
• Continued underdrain work will continue just east of Skunk Hollow Road.
 
Continued roadway maintenance as needed.
 
SLOW DOWN FOR ROUGH ROAD CONDITIONS!
EXPECT DELAYS DURING PEAK HOURS!

VT 117 – July 24, 2018

The anticipated work schedule is as follows:
• Continued shoulder cleanup work from the Essex/Jericho town line working towards Tiffany Lane.
• Continued excavation work between VT 289 and Greenfield Road to remove unsuitable material from roadway.
 
Continued roadway maintenance as needed.
 
SLOW DOWN FOR ROUGH ROAD CONDITIONS!
EXPECT DELAYS DURING PEAK HOURS!

The anticipated work schedule for the week beginning Monday, July 22, 2018 on VT 117:

Monday thru Friday:

  • Continue roadway excavation in various areas between Tiffany Lane to Sand Hill Road.
  • Begin reclaiming the roadway from the Essex/Jericho Town line proceeding north. Reclaim takes 10″ of the road surface and basically rototills it and places it back as a gravel surface, recycling the existing material.
  • ROADWAY MAINTENANCE THROUGHOUT THE PROJECT!

 Motorists please be aware that the roadway surface will be rough for a duration of time – please drive slowly!   

Roadway maintenance will be ongoing, as needed.    

Commuting motorists should seek alternate routes.  Expect delays during peak hours!

VT 117 – July 20, 2018

The anticipated work schedule is as follows:
• Continued guardrail set back work between Sand Hill Road and Tiffany Lane.
• Continued excavation work between Tiffany Lane and VT 289 to remove unsuitable material from roadway.
 
Continued roadway maintenance as needed.
 
SLOW DOWN FOR ROUGH ROAD CONDITIONS!
EXPECT DELAYS DURING PEAK HOURS!

The following is the anticipated schedule for Bridge #8:

Written by on July 19, 2018 in BRIDGE 8 VT ROUTE 17

The following is the anticipated work schedule for the week beginning Monday, July 22, 2018.  

 Monday thru Sunday:

  • Completion of the roadway approaches to the bridge.
  • Paving of the bridge deck
  • Installation of bridge rail & guardrail

This project remains on schedule!

The anticipated work schedule for the I-91 Rockingham Bridges:

Written by on July 19, 2018 in Rockingham Bridges-I91

For the week beginning Monday, July 23, 2018:

I-91 northbound bridge activities:

 Monday thru Friday:

 •  Continued preparation work on the set girders to include concrete pours.

 ALL ROLLING ROAD BLOCKS ARE COMPLETE AT THIS TIME.  MOTORISTS SHOULD NOT ENCOUNTER ANY CONSTRUCTION DELAYS.

The anticipated work schedule for VT 116:

Written by on July 19, 2018 in Middlebury-Starksboro VT 116

The following is the anticipated work schedule for the week beginning Monday,  July 23, 2018:

Monday thru Friday:

  • Continued sign installation and miscellaneous shoulder work throughout the project.

 The culvert work scheduled has been postponed until further notification.

 Motorists should expect minor delays with traffic control present.

 