For the week beginning Monday, July 30, 2018:
Monday thru Friday:
- Cold planning the side road approaches and various approaches on the main line between E. Middlebury and Bristol
- Miscellaneous clean up work throughout the project.
We are awaiting notification on the culvert work that was postponed. I will post it if this gets scheduled for next week.
The anticipated work schedule is as follows:
- Continued shoulder cleanup work within the VT 289 area.
- Continued underdrain work will continue just east of Barber Farm Road, Jericho.
- Begin reclaiming the roadway from the Essex/Jericho Town line proceeding westbound. Reclaim takes 10″ of the road surface and basically rototills it and places it back as a gravel surface, recycling the existing material.
Monday thru Friday:
- Continue roadway excavation in various areas between Tiffany Lane to Sand Hill Road.
- Begin reclaiming the roadway from the Essex/Jericho Town line proceeding north. Reclaim takes 10″ of the road surface and basically rototills it and places it back as a gravel surface, recycling the existing material.
- ROADWAY MAINTENANCE THROUGHOUT THE PROJECT!
Motorists please be aware that the roadway surface will be rough for a duration of time – please drive slowly!
Roadway maintenance will be ongoing, as needed.
Commuting motorists should seek alternate routes. Expect delays during peak hours!
The following is the anticipated work schedule for the week beginning Monday, July 23, 2018:
Monday thru Friday:
- Continued sign installation and miscellaneous shoulder work throughout the project.
The culvert work scheduled has been postponed until further notification.
Motorists should expect minor delays with traffic control present.