VT 117 – July 19, 2018

The anticipated work schedule is as follows:
• Continued guardrail set back work between Sand Hill Road and the Essex/Jericho Town line.
• Begin roadway excavation between Tiffany Lane and Pinewood Drive.
 
Continued roadway maintenance as needed.
 
SLOW DOWN FOR ROUGH ROAD CONDITIONS!
EXPECT DELAYS DURING PEAK HOURS!

VT 117 – July 18, 2018

The anticipated work schedule is as follows:
• Continued guardrail set back work between Sand Hill Road and the Essex/Jericho Town line.
• Continued underdrain work between Tiffany Lane and VT 289.
 
Continued roadway maintenance as needed.
 
SLOW DOWN AND EXPECT DELAYS DURING PEAK HOURS!

VT 117 – July 17, 2018:

• Continued guardrail set back work between Sand Hill Road and the Essex/Jericho Town line.
• Weather permitting, Continued underdrain work between Tiffany Lane and VT 289.
• If rain, structure adjustment work between Tiffany Lane and VT 289.
Contractor will continue roadway maintenance as needed.
 
SLOW DOWN AND EXPECT DELAYS DURING PEAK HOURS.

The anticipated work schedule on VT 117

The anticipated work schedule on VT 117

For the week beginning Monday,  July 16, 2018:

 Monday thru Friday:

  • Continue installing underdrain from Tiffany Lane to Sand Hill Road.
  • Begin culvert work from Tiffany Lane to Sand Hill Road.
  • ROADWAY MAINTENANCE THROUGHOUT THE PROJECT!

Motorists please be aware that the roadway surface will be rough for a duration of time.  Crews will keep up with the maintenance to the best of their ability.  Drive slowly! 

Commuting motorists should seek alternate routes.  Expect delays during peak hours!

Milling 7-11-18

The anticipated work schedule for the I-91 Rockingham Bridges:

Written by on July 12, 2018 in Rockingham Bridges-I91
The anticipated work schedule for the I-91 Rockingham Bridges:

Tomorrow, July 13, 2018 will be the last of the rolling road blocks for the northbound bridge.  The anticipated times are as follows:

  • Southbound:  approx.. 6:00am & 12:00pm for approx. 10 mins.
  • Northbound:  approx.  5:30am & 8:00am for approx.. 20 mins.(the 8:00am will include a repair to a pothole forming)

For the week beginning Monday, July 16, 2018:

 Monday thru Friday:

  • Preparation work on the set girders in anticipation of concrete.

VT 117 July 13, 2018

  • Continued shoulder cleanup from the Essex/Jericho Town line working westbound
  • Continued underdrain work between Sand Hill Road and VT 289 interchange.

MOTORISTS EXPECT DELAYS DURING PEAK HOURS!

Traffic control will be present allowing for one lane of alternating travel.

The anticipated work schedule for VT 116:

Written by on July 12, 2018 in Middlebury-Starksboro VT 116

The following is the anticipated work schedule for the week beginning Monday,  July 16, 2018:

 Monday thru Friday:

  • Continued sign installation between Bristol and Middlebury.

 The culvert work scheduled has been postponed until further notification.

The following is the anticipated schedule for Bridge #8:

Written by on July 12, 2018 in BRIDGE 8 VT ROUTE 17

For the week beginning Monday, July 16, 2018: 

Concrete is being placed on the bridge decking today, July 12, 2018.

 Monday thru Sunday:

  •  Continue building the roadway approaches to the bridge.

 

VT 117 July 12, 2018

• Continued cold planning between Sand Hill Road and the Essex/Jericho town line.

•  Continued shoulder cleanup from the start of the project in Essex to the VT 289 interchange.

•  Continued underdrain work between Sand Hill Road and VT 289 interchange.

MOTORISTS EXPECT DELAYS DURING PEAK HOURS!

Traffic control will be present allowing for one lane of alternating travel.

VT 117 July 11, 2018

•  7:00am – Excavation of blacktop shoulders from VT 289 interchange to the start of the project, approx. Tiffany Lane
•  9:30am Cold planning continues from Sand Hill Road to N. Williston Road.
Traffic control will be present allowing for one lane of alternating travel.
MOTORISTS EXPECT DELAYS DURING PEAK HOURS!