Stephanie Barrett
Our specialty is in construction accounting, we contract with many businesses, offering a variety of accounting/payroll needs. In addition to accounting & bookkeeping services, we offer Public Relations work for job specific road/bridge construction and lease out fully operational office trailers.
The following is an update of the construction to take place for the week beginning Sunday, July 12, 2020.
Southbound I-91 bridge activities resume with limited personnel.
Sunday through Friday- 24 hours/day:
- Bridge deck work to continue
- Placement of concrete and other work at the northbound abutment
- Tree branch trimming within the construction zone on I-91
- Maintenance of traffic control devices continues
NARROW LANES – REDUCED SPEEDS – USE CAUTION!
Please Note: As part of Governor Scott’s “Work Smart, Stay Safe” order, all construction crews are currently subject to safety restrictions and precautions.
The following is an update of the construction to take place for the week beginning Monday, July 01, 2020.
Southbound I-91 bridge activities resume with limited personnel.
Monday through Friday- 24 hours/day:
- Bridge deck work to continue
- Maintenance of traffic control devices continues
NARROW LANES – REDUCED SPEEDS – USE CAUTION!
Please Note: As part of Governor Scott’s “Work Smart, Stay Safe” order, all construction crews are currently subject to safety restrictions and precautions.
The following is an update of the construction to take place for the week beginning Monday, June 29, 2020.
Southbound I-91 bridge activities resume with limited personnel.
Monday through Friday- 6:00 a.m. to 5:00 p.m.:
- Bridge deck work to continue
- Maintenance of traffic control devices continues
Please Note: As part of Governor Scott’s “Work Smart, Stay Safe” order, all construction crews are currently subject to safety restrictions and precautions.
NARROW LANES – REDUCED SPEEDS – USE CAUTION!
This is the final update for this project. You may see some minor activity, but it should not affect the traveling public.
On behalf of the VT Agency of Transportation and myself, we would like to thank everyone for your patience and understanding during the construction.
We hope you enjoy the improvements, not only for your safety, but also for the smooth ride.
May you all stay safe and well!
The following is an update of the construction to take place for the week beginning Monday, June 22, 2020.
Southbound I-91 bridge activities resume with limited personnel.
Monday – 6:00 a.m. to noon:
Tuesday through Friday (Saturday, if necessary) – 2:00 a.m. until noon:
- Bridge deck work to continue
- Maintenance of traffic control devices continues
Please Note: As part of Governor Scott’s “Work Smart, Stay Safe” order, all construction crews are currently subject to safety restrictions and precautions.
NARROW LANES – REDUCED SPEEDS – USE CAUTION!
The following is an update of the construction to take place for the week beginning Monday, June 15, 2020.
Southbound I-91 bridge activities resume with limited personnel.
Monday through Friday:
- Continue bridge deck work
- Demolition work the old Pier 3 footing
- Prep work at Abutment 2
- Continue maintenance of traffic control devises
MONDAY, JUNE 11, 2020 – ROLLING ROAD BLOCKS:
Due to some necessary roadway maintenance, Beginning at Exit 5 northbound, motorists can expect a rolling road block beginning at 8:00 a.m. with another at 10:00 a.m., if necessary, causing approximately a 20-minute delay.
Beginning at Exit 7 southbound, motorists can expect a rolling road block beginning at 12:30 p.m. with another at 1:30 p.m., if necessary, causing approximately a 20-minute delay.
Please Note: As part of Governor Scott’s “Work Smart, Stay Safe” order, all construction crews are currently subject to safety restrictions and precautions.
NARROW LANES – REDUCED SPEEDS – USE CAUTION!
The following is an update of the construction to take place for the week beginning Monday, June 08, 2020.
Southbound I-91 bridge activities resume with limited personnel.
Monday through Friday:
- Continue bridge deck work
- Continue maintenance of traffic control devises
THURSDAY, JUNE 11, 2020 – ROLLING ROAD BLOCKS:
Due to some necessary roadway maintenance, Beginning at Exit 5 northbound, motorists can expect a rolling road block beginning at 8:00 a.m. with another at 10:00 a.m., if necessary, causing approximately a 20-minute delay.
Beginning at Exit 7 southbound, motorists can expect a rolling road block beginning at 12:30 p.m. with another at 1:30 p.m., if necessary, causing approximately a 20-minute delay.
Please Note: As part of Governor Scott’s “Work Smart, Stay Safe” order, all construction crews are currently subject to safety restrictions and precautions.
NARROW LANES – REDUCED SPEEDS – USE CAUTION!
The following is the anticipated daytime work schedule for the week beginning Sunday, May 31, 2020:
Sunday & Monday (subsequent nights if necessary) – 6:00 p.m. to 6:00 a.m.:
- Weather permitting, pavement markings throughout the project limits
Traffic control will be present during all activities allowing for one lane of alternating traffic. Motorists may encounter minor delays.
Monday through Friday – 6:00 a.m. to 5:30 p.m.:
- Project cleanup throughout
Two-way traffic will be maintained.
As part of Governor Scott’s “Work Smart, Stay Safe” order, all construction crews are currently subject to safety restrictions and precautions.
Connect