ESSEX, JERICHO-RICHMOND VT ROUTE 117

The Vermont Agency of Transportation along with Pike Industries Inc. will begin this 2018 – 2019 roadway rehabilitation project of VT Route 117 beginning in Essex where the State Highway begin to the intersection Route 2 in Richmond the week beginning June 18, 2018.  The anticipated completion date is October 11, 2019.

This project will consist of rehabilitation of the existing roadway sub-base, new traveling surface with shoulder widening (where feasible), drainage, guardrail and signage upgrades, new signal at the intersection of 289 off ramp and VT 117 along with other incidental items throughout the project.

During the construction period, motorists should expect traffic flow to be maintained at all times with one-way alternating traffic during construction hours with control present.

Motorists should also expect to be traveling on a gravel surface from approximately mid-July 2018 through August 2018.from Essex where the State Highway begins to the Jericho town line.

Anyone with questions or concerns regarding the project may contact Stephanie Barrett, Public Outreach Coordinator at 802-862-6085.

The anticipated work schedule on VT 117 for May 21, 2019

  • Continue roadway excavation, shaping and drainage work between Bradley Bow Road and Barber Farm Road
  • General cleanup work and roadway maintenance

Motorist should expect delays!

MOTORISTS PLEASE SLOW DOWN!  SAFETY FIRST!

Traffic control will be present allowing for one-lane of alternating travel within the construction zones. 

The anticipated work schedule for the week beginning May 20, 2019

Monday thru Friday @ noon:

  • Continue roadway shaping throughout the project limits
  • General cleanup work and roadway maintenance

Motorist should expect delays!

MOTORISTS PLEASE SLOW DOWN!  SAFETY FIRST!

Traffic control will be present allowing for one-lane of alternating travel within the construction zones. 

The anticipated work schedule on VT 117 for May 17, 2019

  • Continue roadway excavation, shaping and drainage work from Bradley Bow Road and Barber Farm Road
  • General cleanup work and roadway maintenance

Motorist should expect delays!

MOTORISTS PLEASE SLOW DOWN!  SAFETY FIRST!

Traffic control will be present allowing for one-lane of alternating travel within the construction zones. 

The anticipated work schedule for May 16, 2019

  • Continue roadway excavation, shaping and drainage work from Bradley Bow Road and Barber Farm Road
  • General cleanup work and roadway maintenance

Motorist should expect delays!

MOTORISTS PLEASE SLOW DOWN!  SAFETY FIRST!

Traffic control will be present allowing for one-lane of alternating travel within the construction zones. 

The anticipated work schedule for May 15, 2019

  • Continue roadway excavation and drainage just east of Bradley Bow Road
  • Roadway shaping within the Barber Farm Road area
  • General cleanup work and roadway maintenance

Motorist should expect delays!

MOTORISTS PLEASE SLOW DOWN!  SAFETY FIRST!

Traffic control will be present allowing for one-lane of alternating travel within the construction zones. 

The anticipated work schedule for May 14, 2019

  • Continue roadway excavation and drainage improvements between Barber Farm Road and Bradley Bow Road
  • Continue guardrail work within the Skunk Hollow Road location
  • Roadway shaping throughout the project limits
  • General cleanup work and roadway maintenance

Motorist should expect delays!

MOTORISTS PLEASE SLOW DOWN!  SAFETY FIRST!

Traffic control will be present allowing for one-lane of alternating travel within the construction zones. 

The anticipated work schedule on VT 117 for the week beginning May 13, 2019

Monday & Tuesday:

  • Continue guardrail work within the Skunk Hollow Road location

Monday thru Friday:

  • Continued roadway excavation and drainage improvements between Barber Farm Road and Bradley Bow Road
  • Roadway shaping throughout the project limits

Monday thru Sunday:

  • General cleanup work and roadway maintenance

Motorist should expect delays!

MOTORISTS PLEASE SLOW DOWN!  SAFETY FIRST!

Traffic control will be present allowing for one-lane of alternating travel within the construction zones. 

The anticipated work on VT-117 for May 10, 2019

  • Continued roadway excavation and shaping between Barber Farm and Bradley Bow Roads
  • Continued guardrail work between the Essex/Jericho town line and Skunk Hollow

Motorist should expect delays!
MOTORISTS PLEASE SLOW DOWN! SAFETY FIRST!

The anticipated work for May 09, 2019 is as follows:

  • Continued roadway excavation between the Essex/Jericho town line and Skunk Hollow
  • Continued roadway shaping between Skunk Hollow and Barber Farm Roads
  • Continued guardrail work between Bradley Bow and Rogers Lane

Motorist should expect delays!
MOTORISTS PLEASE SLOW DOWN! SAFETY FIRST!

The anticipated road work on VT 117 for May 08, 2019

  • Continued roadway excavation between the Essex/Jericho town line and Skunk Hollow
  • Continued roadway shaping between Rogers Lane and the US Route 2 & VT 117 intersection
  • 9am to 3pm VTrans will be working within the N. Williston Road intersection

Motorist should expect delays!
MOTORISTS PLEASE SLOW DOWN! SAFETY FIRST!