ESSEX, JERICHO-RICHMOND VT ROUTE 117

The Vermont Agency of Transportation along with Pike Industries Inc. will begin this 2018 – 2019 roadway rehabilitation project of VT Route 117 beginning in Essex where the State Highway begin to the intersection Route 2 in Richmond the week beginning June 18, 2018.  The anticipated completion date is October 11, 2019.

This project will consist of rehabilitation of the existing roadway sub-base, new traveling surface with shoulder widening (where feasible), drainage, guardrail and signage upgrades, new signal at the intersection of 289 off ramp and VT 117 along with other incidental items throughout the project.

During the construction period, motorists should expect traffic flow to be maintained at all times with one-way alternating traffic during construction hours with control present.

Motorists should also expect to be traveling on a gravel surface from approximately mid-July 2018 through August 2018.from Essex where the State Highway begins to the Jericho town line.

Anyone with questions or concerns regarding the project may contact Stephanie Barrett, Public Outreach Coordinator at 802-862-6085.

The anticipated work on VT 117 for May 07, 2019

• Continued roadway excavation between the Essex/Jericho town line and Skunk Hollow

• Continued roadway shaping between Rogers Lane and the US Route 2 & VT 117 intersection

• 9am to 3pm VTrans will be working within the N. Williston Road intersection

Motorist should expect delays!
MOTORISTS PLEASE SLOW DOWN! SAFETY FIRST!

The anticipated work schedule on VT 117 for the week beginning May 6, 2019

Monday thru Friday:

  • Continued roadway excavation and drainage improvements
  • Roadway shaping
  • Continued guardrail work

Motorist should expect delays!

MOTORISTS PLEASE SLOW DOWN!  SAFETY FIRST!

Traffic control will be present allowing for one-lane of alternating travel within the construction zones. 

The anticipated work on VT 117 for May 03, 2019

  • Fine grading/roadway shaping around the US Route 2/VT 117 intersection
  • Continued drainage improvements and guardrail work between the Essex/Jericho town line and Barber Farm Road.

Motorists should expect delays!

MOTORISTS PLEASE SLOW DOWN! 
SAFETY FIRST!
SPEED LIMIT WILL BE ENFORCED!

The anticipated work schedule on VT 117 for May 02, 2019

  • 8:30am Reclaiming of the roadway surface continues in Richmond between the US Route 2/VT 117 intersection to Rogers Lane. Motorists can expect moderate to long delays.
  • 7:00am Continued drainage improvements and guardrail work between the Essex/Jericho town line and Barber Farm Road.

MOTORISTS PLEASE SLOW DOWN! 
SAFETY FIRST!
SPEED LIMIT WILL BE ENFORCED!

The anticipated work schedule on VT 117 for May 01, 2019

  • Reclaiming of the roadway surface continues from north 
    of Bradley Bow Road, Jericho to Rogers Lane, 
    Richmond.
  • Continued drainage improvements from the
    Essex/Jericho town line to Skunk Hollow Road.
  • Continue guardrail work from the Essex/Jericho town line
    to Skunk Hollow Road.

USE CAUTION – DRIVE SLOW!

The anticipated work schedule on VT 117 for April 30, 2019

  • Reclaiming of the roadway surface from Barber Farm Road to Rogers Lane. 
  • Continue guardrail work from Barber Farm Road to Skunk Hollow Road.
  • Continued drainage improvements from the Essex/Jericho town line to Skunk Hollow Road.

USE CAUTION – DRIVE SLOW!

The anticipated work schedule on VT 117 for the week beginning April 29, 2019

Monday thru Friday:

  • Reclaiming of the roadway surface between Skunk Hollow Road and the VT Route 117/US Route 2 intersection. 
  • Roadway excavation to begin at the Essex/Jericho town line proceeding east throughout the week.
  • Signal work at the intersection of VT 289 and VT Route 117.

Monday thru Wednesday:

  • Continued Guardrail work throughout the project limits.

Motorist should expect delays!

Traffic control will be present allowing for one-lane of alternating travel within the construction zones. 

The anticipated work schedule on VT 117 for April 26, 2019

  • Reclaiming of the roadway surface from the Essex/Jericho town line to Skunk Hollow Road. 
  • Continue signal work at the VT 289 / 117 intersection.
  • Continued shoulder work throughout the project limits.

USE CAUTION – DRIVE SLOW!

The anticipated work schedule on VT 117 for April 25, 2019

  • Continue signal work at the VT 289 / 117 intersection.
  • Guardrail work to continue throughout the project.
  • Continued shoulder work between Barber Farm Road and Skunk Hollow Road.
  • Continued cold planing (grinding) from Skunk Hollow Road to the Essex/Jericho town line.

USE CAUTION – DRIVE SLOW!

The anticipated work schedule on VT 117 for April 24, 2019:

  • Continue signal work at the VT 289 / 117 intersection.
  • Guardrail work to continue throughout the project.
  • Cleanup work between Bradley Bow Road and Barber Farm Road.
  • Continued cold planing (grinding) between Barber Farm Road and Skunk Hollow Road.

USE CAUTION – DRIVE SLOW!