ESSEX, JERICHO-RICHMOND VT ROUTE 117

The Vermont Agency of Transportation along with Pike Industries Inc. will begin this 2018 – 2019 roadway rehabilitation project of VT Route 117 beginning in Essex where the State Highway begin to the intersection Route 2 in Richmond the week beginning June 18, 2018.  The anticipated completion date is October 11, 2019.

This project will consist of rehabilitation of the existing roadway sub-base, new traveling surface with shoulder widening (where feasible), drainage, guardrail and signage upgrades, new signal at the intersection of 289 off ramp and VT 117 along with other incidental items throughout the project.

During the construction period, motorists should expect traffic flow to be maintained at all times with one-way alternating traffic during construction hours with control present.

Motorists should also expect to be traveling on a gravel surface from approximately mid-July 2018 through August 2018.from Essex where the State Highway begins to the Jericho town line.

Anyone with questions or concerns regarding the project may contact Stephanie Barrett, Public Outreach Coordinator at 802-862-6085.

The anticipated work schedule on VT 117 for April 23, 2019

  • Continue signal work at the VT 289 / 117 intersection.
  • Guardrail work to continue throughout the project.
  • Cleanup work between Rogers Lane and Bradley Bow Road.
  • Continued cold planing (grinding) between Barber Farm Road and Skunk Hollow Road.

USE CAUTION – DRIVE SLOW!

The anticipated work schedule on VT 117 for the week beginning April 22, 2019

The anticipated work schedule on VT 117 for the week beginning April 22, 2019

Monday thru Wednesday:
• Continued grinding the existing pavement from Barber Farm Road to the Essex/Jericho town line.

Tuesday thru Friday:
• Signal work at the intersection of VT 289 and VT Route 117.
• Continue drainage improvements between the Essex/Jericho town line and Skunk Hollow Road.
• Shoulder cleanup between the intersection of VT Route 117 & US Route 2 and the Essex/Jericho town line.
• Guardrail work throughout the project limits.

Traffic control will be present allowing for one-lane of alternating travel within the construction zones. Motorist should expect delays and use caution.

The anticipated work schedule on VT 117 for April 19, 2019:

  • 7:00 a.m. Continued drainage & slope improvements from Barber Farm Road to the Essex/Jericho town line.
  • 7:00 a.m. Guardrail work between VT Route 2/117 intersection and Rogers lane.
  • 8:30 a.m. Continued grinding milling between Rogers Lane and Bradley Bow Road.

Motorists should expect delays! 

Be aware that travel is reduced to one lane with traffic control present within the construction zones.

The anticipated work schedule on VT 117 for April 18, 2019:

  • 7:00 a.m. Continued drainage & slope improvements from Barber Farm Road to the Essex/Jericho town line.
  • 7:00 a.m. Guardrail work between VT Route 2/117 intersection and Rogers lane.
  • 8:30 a.m. Continued grinding milling between Rogers Lane and Bradley Bow Road.

Motorists should expect delays! 

Be aware that travel is reduced to one lane with traffic control present within the construction zones.

The anticipated work schedule on VT 117 for April 17, 2019:

  • 7:00 a.m. Continued drainage & slope improvements from Barber Farm Road to the Essex/Jericho town line.
  • 8:30 a.m. Continued grinding milling between Rogers Lane and Bradley Bow Road.

Motorists should expect delays! 

Be aware that travel is reduced to one lane with traffic control present within the construction zones.

The anticipated work schedule on VT 117 for April 16, 2019:

The anticipated work schedule on VT 117 for April 16, 2019:
  • 7:00 a.m. Continued drainage improvements from Barber Farm Road to the Essex/Jericho town line.
  • 8:30 a.m. Continued grinding of the existing pavement (milling) from
    the intersection of VT Route 117 & US Route 2 to the Essex/Jericho town line.

Motorists should expect delays!

Be aware that travel is reduced to one lane with traffic control present within the construction zones.

The anticipated work schedule for the week beginning April 15, 2019:

Monday thru Friday:
• Grinding the existing pavement from the intersection of VT Route 117 & US Route 2 to the Essex/Jericho town line.
• Continue drainage improvements between the Essex/Jericho town line and Skunk Hollow Road.
• Continue slope repairs between the Essex/Jericho town line and the intersection of VT Route 117 & US Route 2.

Tuesday thru Friday:
• Signal work at the intersection of VT 289 and VT Route 117.

Wednesday thru Friday:
• Installation of barrier between the Essex/Jericho town line and the intersection of VT Route 117 & US Route 2.

Thursday & Friday:
• Roadway excavation between Barber Farm Road and Bradley Bow Road.

Motorists should expect delays!

Be aware that travel is reduced to one lane with traffic control present within the construction zones.

The anticipated work schedule on VT 117 for April 12, 2019:

  • Continued drainage and slope clearing between Skunk Hollow Road and the Essex/Jericho town line.
  • Slope stabilization work between Bradley Bow Road and the Jericho/Richmond town line

Motorists should expect delays!

Be aware that travel is reduced to one lane with traffic control present within the construction zones.

The anticipated work schedule on VT 117

Thursday, April 11, 2019:

  • Continued drainage and slope clearing between Skunk Hollow Road and the Essex/Jericho town line.

Motorists should expect delays!

Be aware that travel is reduced to one lane with traffic control present within the construction zones.

The anticipated work schedule on VT Route 117

Wednesday, April 10, 2019:

  • Continued drainage and slope clearing between Skunk Hollow Road and the Essex/Jericho town line.
  • Slope stabilization work between Bradley Bow Road and the Jericho/Richmond town line

Motorists should expect delays!

Be aware that travel is reduced to one lane with traffic control present within the construction zones.