ESSEX, JERICHO-RICHMOND VT ROUTE 117
The Vermont Agency of Transportation along with Pike Industries Inc. will begin this 2018 – 2019 roadway rehabilitation project of VT Route 117 beginning in Essex where the State Highway begin to the intersection Route 2 in Richmond the week beginning June 18, 2018. The anticipated completion date is October 11, 2019.
This project will consist of rehabilitation of the existing roadway sub-base, new traveling surface with shoulder widening (where feasible), drainage, guardrail and signage upgrades, new signal at the intersection of 289 off ramp and VT 117 along with other incidental items throughout the project.
During the construction period, motorists should expect traffic flow to be maintained at all times with one-way alternating traffic during construction hours with control present.
Motorists should also expect to be traveling on a gravel surface from approximately mid-July 2018 through August 2018.from Essex where the State Highway begins to the Jericho town line.
Anyone with questions or concerns regarding the project may contact Stephanie Barrett, Public Outreach Coordinator at 802-862-6085.
The following is an update to the work schedule for the week beginning Monday, April 08, 2019:
Monday thru Friday:
• Weather permitting, drainage work to continue between the Essex/Jericho town line and Skunk Hollow Road
• Slope repairs between Bradley Bow Road, Jericho and Rogers Lane, Richmond
Tuesday thru Friday:
• Signal work at the intersection of VT 289 and VT Route 117
Traffic control will be present allowing for one-lane of alternating travel within the construction zones. Motorists please use caution!
It’s that time of the year again!
The following is an update to the work schedule for the week beginning Monday, April 01, 2019:
Monday & Tuesday:
- Traffic control sign packages to be installed
Wednesday thru Friday:
- Weather permitting, ledge removal and underdrain work to begin between the Essex/Jericho town line and Skunk Hollow Road
The following is an update to the work schedule for the week beginning Monday, December 17, 2018:
- Last week! Weather permitting, continued line markings will occur, motorists will encounter minor delays with traffic control present.
***** This is the last update that will be sent until April 2019 *****
The following is the anticipated work schedule:
- Weather permitting, continued pavement markings between Valley View Drive and Sand Hill Road. Traffic control will be present allowing for one lane of alternating traffic.
Motorists should expect minor delays.
Please use caution when traveling thru the construction zone.
The following is the anticipated work schedule:
- Weather permitting, pavement markings between Valley View Drive and Sand Hill Road. Traffic control will be present allowing for one lane of alternating traffic.
Motorists should expect minor delays.
Please use caution when traveling thru the construction zone.
The following is the anticipated work schedule:
- Weather permitting, pavement markings between Valley View Drive and Sand Hill Road. Traffic control will be present allowing for one lane of alternating traffic.
Motorists should expect minor delays.
Please use caution when traveling thru the construction zone.