ESSEX, JERICHO-RICHMOND VT ROUTE 117

The Vermont Agency of Transportation along with Pike Industries Inc. will begin this 2018 – 2019 roadway rehabilitation project of VT Route 117 beginning in Essex where the State Highway begin to the intersection Route 2 in Richmond the week beginning June 18, 2018.  The anticipated completion date is October 11, 2019.

This project will consist of rehabilitation of the existing roadway sub-base, new traveling surface with shoulder widening (where feasible), drainage, guardrail and signage upgrades, new signal at the intersection of 289 off ramp and VT 117 along with other incidental items throughout the project.

During the construction period, motorists should expect traffic flow to be maintained at all times with one-way alternating traffic during construction hours with control present.

Motorists should also expect to be traveling on a gravel surface from approximately mid-July 2018 through August 2018.from Essex where the State Highway begins to the Jericho town line.

Anyone with questions or concerns regarding the project may contact Stephanie Barrett, Public Outreach Coordinator at 802-862-6085.

The anticipated work schedule on VT 117 for the week beginning October 14, 2019

Written by on October 10, 2019 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

Monday – No work due to the Columbus Day holiday

Tuesday through Friday:

  • Weather permitting, continue pavement markings from Sand Hill Road to Route 2.
  • Continue mailbox adjustments
  • Project cleanup work

MOTORISTS SHOULD EXPECT MINIMAL DELAYS!

Traffic control will be present allowing for one-lane of alternating travel within the construction zones.  The speed limit will be enforced!

PLEASE SLOW DOWN!  SAFETY FIRST!

The anticipated work schedule for October 11, 2019 until noon

Written by on October 10, 2019 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
  • Continue pavement markings

MOTORISTS CAN EXPECT MINIMAL DELAYS!

The anticipated work schedule on VT 117 for October 10, 2019

Written by on October 9, 2019 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
  • Weather permitting, continue pavement markings
  • Continue sign installation
  • Continue mailbox adjustments
  • General cleanup work

PLEASE SLOW DOWN!  SAFETY FIRST!

The anticipated work schedule for October 9, 2019

Written by on October 8, 2019 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
  • Weather permitting, continue pavement markings
  • Continue sign installation
  • Continue mailbox adjustments
  • General cleanup work

PLEASE SLOW DOWN!  SAFETY FIRST!

The anticipated work schedule for October 8, 2019

Written by on October 7, 2019 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
  • Weather permitting, continue driveway tie-ins.
  • Weather permitting, continue pavement markings
  • Continue sign installation

PLEASE SLOW DOWN!  SAFETY FIRST!

The following work schedule on VT 117 for the week beginning Saturday, October 5, 2019

Written by on October 3, 2019 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

Saturday, Monday through Friday:

  • Weather permitting, continue pavement markings
  • Continue sign installation
  • Continue mailbox adjustments
  • General cleanup work

Monday:

  • Completion of shoulder work

Tuesday & Wednesday:

  • Weather permitting, completion of paving driveway tie-ins.

MOTORISTS SHOULD PLAN FOR DELAYS

Traffic control will be present allowing for one-lane of alternating travel within the construction zones.  The speed limit will be enforced!

PLEASE SLOW DOWN!  SAFETY FIRST!

The anticipated work schedule for VT 117 on October 4, 2019

Written by on October 3, 2019 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
  • Weather permitting, pavement markings throughout the project limits
  • Continue shoulder work throughout the project limits
  • Continue sign installation
  • Mailbox adjustments throughout the project limits
  • General cleanup work throughout the project limits

MOTORISTS SHOULD PLAN FOR DELAYS

Traffic control will be present allowing for one-lane of alternating travel within the construction zone.

The anticipated work schedule on VT 117 for October 3, 2019

Written by on October 2, 2019 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
  • Weather permitting, pavement markings throughout the project limits
  • Continue shoulder work throughout the project limits
  • Continue sign installation
  • Mailbox adjustments throughout the project limits
  • General cleanup work throughout the project limits

MOTORISTS SHOULD PLAN FOR DELAYS

Traffic control will be present allowing for one-lane of alternating travel within the construction zone.

The anticipated work schedule for VT 117 on October 2, 2019

Written by on October 1, 2019 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
  • Weather permitting, completion of driveway tie-ins.
  • Continue shoulder work throughout the project limits
  • General cleanup work throughout the project limits

MOTORISTS SHOULD PLAN FOR DELAYS

Traffic control will be present allowing for one-lane of alternating travel within the construction zones.  The speed limit will be enforced!

The anticipated work schedule on VT 117 for October 1, 2019

Written by on October 1, 2019 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
  • Weather permitting, continue paving abutting side roads and driveway tie-ins.
  • Continue shoulder work throughout the project limits
  • Weather permitting, pavement markings throughout the project limits
  • Continue sign installation
  • General cleanup work throughout the project limits

MOTORISTS SHOULD PLAN FOR DELAYS

Traffic control will be present allowing for one-lane of alternating travel within the construction zones.  The speed limit will be enforced!

Top