ESSEX, JERICHO-RICHMOND VT ROUTE 117
The Vermont Agency of Transportation along with Pike Industries Inc. will begin this 2018 – 2019 roadway rehabilitation project of VT Route 117 beginning in Essex where the State Highway begin to the intersection Route 2 in Richmond the week beginning June 18, 2018. The anticipated completion date is October 11, 2019.
This project will consist of rehabilitation of the existing roadway sub-base, new traveling surface with shoulder widening (where feasible), drainage, guardrail and signage upgrades, new signal at the intersection of 289 off ramp and VT 117 along with other incidental items throughout the project.
During the construction period, motorists should expect traffic flow to be maintained at all times with one-way alternating traffic during construction hours with control present.
Motorists should also expect to be traveling on a gravel surface from approximately mid-July 2018 through August 2018.from Essex where the State Highway begins to the Jericho town line.
Anyone with questions or concerns regarding the project may contact Stephanie Barrett, Public Outreach Coordinator at 802-862-6085.
- Weather permitting, paving to begin at the Essex/Jericho town line working westbound.
- Underdrain work continues between the Jericho/Richmond town line and the US Route 2 intersection.
- 7:00am Weather permitting, paving to continue between Essex/Jericho town line and Sand Hill Road.
- 7:00am Continued structure work within the VT-289 area.
- 9:00am Underdrain work continues between the Jericho/Richmond town line and the US Route 2 intersection.
- 8:00am Weather permitting, paving to begin at the Essex/Jericho town line working westbound.
- 9:00am Underdrain work continues between the Jericho/Richmond town line and the US Route 2 intersection.
- 7:00am Continued structure work within the VT-289 area.
- Shoulder/Ditch work continues between the Essex/Jericho town line and N. Williston Road.
- Underdrain & culvert work continues between the Jericho/Richmond town line and the US Route 2 intersection.
- Continued structure work within the VT-289 area.
- Shoulder/Ditch work continues between the Essex/Jericho town line and Barber Farm Road.
- Underdrain work continues between the Jericho/Richmond town line and the US Route 2 intersection.
- Continued installation of cold mix in the N. Williston Road intersection.
For the week beginning Saturday, September 15, 2018:
Saturday, Monday & Tuesday:
- Weather permitting, continued installation of cold mix from the Sand Hill Road proceeding west to Tiffany Lane.
Monday thru Friday:
- Shoulder/Ditch work continues between the Essex/Jericho town line and Tiffany Lane.
- Underdrain work continues between the Jericho/Richmond town line and the US Route 2 intersection.
Thursday & Friday:
- Weather permitting, paving begins.
COMMUTING MOTORISTS SHOULD SEEK ALTERNATE ROUTES. EXPECT DELAYS DURING PEAK HOURS!
MOTORISTS PLEASE USE CAUTION WHILE TRAVELING THRU THE WORK ZONE AND DRIVE SLOW!
The anticipated work schedule is as follows:
- Weather permitting, continued installation of cold mix between Sand Hill Road and Tiffany Lane.
- Shoulder clean up and ditch work continues between the Essex/Jericho town line and N. Williston Road.
MOTORISTS PLEASE USE CAUTION WHILE TRAVELING THRU THE WORK ZONE AND DRIVE SLOW!
Commuting motorists should seek alternate routes. Expect delays during peak hours!
The anticipated work schedule is as follows:
Motorists should expect long delays between 2pm & 7pm between N. Williston Road and Sand Hill Road
- Weather permitting, continued installation of cold mix between the Essex/Jericho town line and Sand Hill Road.
- Shoulder clean up and ditch work continues between Valley View Drive and Tiffany Lane.
MOTORISTS PLEASE USE CAUTION WHILE TRAVELING THRU THE WORK ZONE AND DRIVE SLOW!
Commuting motorists should seek alternate routes. Expect delays during peak hours!
The anticipated work schedule is as follows:
Motorists should expect long delays between 2pm & 7pm between N. Williston Road and Sand Hill Road
- Weather permitting, continued installation of cold mix between the Essex/Jericho town line and Sand Hill Road.
- Underdrain work continues between Barber Farm Road and the Jericho/Richmond town line.
- Shoulder clean up and ditch work continues between Valley View Drive and Tiffany Lane.
MOTORISTS PLEASE USE CAUTION WHILE TRAVELING THRU THE WORK ZONE AND DRIVE SLOW!
Commuting motorists should seek alternate routes. Expect delays during peak hours!
The anticipated work schedule is as follows:
- Underdrain work continues between Barber Farm Road and the Jericho/Richmond town line.
- Slope stabilization work continues near the VT-117 & US Route 2 intersection.
MOTORISTS PLEASE USE CAUTION WHILE TRAVELING THRU THE WORK ZONE AND DRIVE SLOW!
Commuting motorists should seek alternate routes. Expect delays!