The Vermont Agency of Transportation along with Pike Industries Inc. will begin this 2018 – 2019 roadway rehabilitation project of VT Route 117 beginning in Essex where the State Highway begin to the intersection Route 2 in Richmond the week beginning June 18, 2018. The anticipated completion date is October 11, 2019.
This project will consist of rehabilitation of the existing roadway sub-base, new traveling surface with shoulder widening (where feasible), drainage, guardrail and signage upgrades, new signal at the intersection of 289 off ramp and VT 117 along with other incidental items throughout the project.
During the construction period, motorists should expect traffic flow to be maintained at all times with one-way alternating traffic during construction hours with control present.
Motorists should also expect to be traveling on a gravel surface from approximately mid-July 2018 through August 2018.from Essex where the State Highway begins to the Jericho town line.
Anyone with questions or concerns regarding the project may contact Stephanie Barrett, Public Outreach Coordinator at 802-862-6085.
For the week beginning Monday, July 02, 2018:
Monday to Tuesday @ noon; Thursday & Friday:
- Continue installing underdrain from the intersection of VT 289 to N. Williston Road on the east side of the roadway.
- Continue thinning and trimming trees between N. Williston Road to the Route 2 Intersection.
Wednesday:
- No work due to the Independence Day Holiday
Commuting motorists should seek alternate routes. Traffic will be delayed during peak hours. Traffic control will be present allowing for one lane of alternating traffic within the construction areas.
The following is the anticipated work schedule for the week beginning Monday, June 25, 2018:
Monday thru Friday:
- Begin installing under drain from the intersection of 289 to N. Williston Road on the east side of the roadway.
- Thinning and trimming trees between 289 to N. Williston Road
- Preventative roadway maintenance at the On/Off Ramps at the 289 & 117 intersections.
Commuting motorists should seek alternate routes. Traffic will be delayed during peak hours. Traffic control will be present allowing for one lane of alternating traffic within the construction areas.