Middlebury-Starksboro VT 116

 

This project extends along VT 116 for approximately 20 miles from just south of Robinson School in Starksboro to the US 7/VT 116 intersection in Middlebury.  Paving within Bristol Village is not included in this project.

MOTORISTS PLEASE USE CAUTION WHILE TRAVELING THRU THE CONSTRUCTION ZONE!

Anyone with questions or concerns regarding this project may contact Stephanie Barrett, Public Outreach Coordinator at 802-862-6085.

If you would like to receive a weekly update of the contractors anticipated work schedule, please email [email protected] your request.

PUT YOUR CELL PHONE DOWN!

IT IS AGAINST THE LAW TO USE HAND HELD DEVICES WHILE DRIVING. IF CAUGHT, YOU WILL BE FINED AND 2 POINTS GO ON YOUR LICENSE!

The following is the anticipated work schedule for the VT 116 project:

Written by on June 29, 2018 in Middlebury-Starksboro VT 116

For the week beginning Monday,  July 02, 2018:

Monday to Tuesday @ noon; Thursday & Friday:

  • Continued shoulder cleanup between Cobble Road, New Haven & Quarry Road, E. Middlebury.
  • Sign installation between Bristol and Starksboro
  • Begin culvert replacement between VT-125 intersection to Cady Road. This culvert replacement will cause 1-way traffic controlled by a traffic signal with a 10’ wide lane restriction.

 Wednesday – No work due to the Independence Day holiday. 

 Motorists should expect delays as traffic control will be present allowing for one lane of alternating traffic within the construction areas.

The following is the anticipated work schedule for the VT 116 project:

Written by on June 21, 2018 in Middlebury-Starksboro VT 116

For the week beginning Monday, June 25, 2018:

Monday thru Friday:

  • Continued shoulder cleanup between Notch Road, Bristol & Quarry Road, E. Middlebury.
  • Begin shoulder widening between VT 125 & Airport Road for storm water pipe crossing.

The following is the anticipated work schedule for the VT 116 project:

Written by on June 14, 2018 in Middlebury-Starksboro VT 116

The anticipated work schedule for the week beginning Monday,  June 18, 2018:

 Monday thru Friday:

  • Continued ditch work. Between East Middlebury and Bristol
  • Sign installation from the “Lord’s Prayer Rock” to Starksboro

Traffic control will be present allowing for one lane of alternating traffic within the construction packages.

The following is the anticipated schedule for VT Route 116:

Written by on June 7, 2018 in Middlebury-Starksboro VT 116

The following is the anticipated work schedule for the week beginning Monday, June 11, 2018:

All work this week will be between East Middlebury/Middlebury to Bristol on VT 116

Monday thru Friday:

  • Continued ditch work.

 Motorists should expect delays as traffic control will be present allowing for one lane of alternating traffic within the construction areas.

The following is the anticipated schedule for VT Route 116:

Written by on May 31, 2018 in Middlebury-Starksboro VT 116

The following is the anticipated work schedule for the week beginning Monday, June 04, 2018:

All work this week will be between East Middlebury/Middlebury to Bristol on VT 116

Monday thru Friday:

  • Continued guardrail replacement and ditch work.

 Motorists should expect delays as traffic control will be present allowing for one lane of alternating traffic within the construction areas.

The following is the anticipated schedule for VT Route 116:

Written by on May 24, 2018 in Middlebury-Starksboro VT 116

For the week beginning Monday, May 28, 2018:

All work this week will be between East Middlebury/Middlebury to Bristol on VT 116

Monday:

  • No work due to the Memorial Day Holiday.

 Tuesday & Wednesday:

  • Weather permitting, continued paving.

Tuesday thru Friday:

  • Continued various operations to include guardrail replacement and ditch work.

 Motorists should expect delays as traffic control will be present allowing for one lane of alternating traffic within the construction areas.

 

The anticipated schedule for the week beginning Monday, May 21, 2018:

All work this week will be between East Middlebury/Middlebury to Bristol on VT 116

 Monday thru Wednesday:

  • Weather permitting, continued paving.

 Monday thru Friday:

  • Various operations to include guardrail replacement and ditch work.

 Motorists should expect delays as traffic control will be present allowing for one lane of alternating traffic within the construction areas.

The following is the anticipated work schedule for the week beginning Monday, May 14, 2018:

Written by on May 10, 2018 in Middlebury-Starksboro VT 116

Monday thru Friday:

  • Weather permitting, paving begins on VT 116 from the southern end Route 7 intersection proceeding north to Bristol.

 Motorists should expect delays as traffic control will be present allowing for one lane of alternating traffic within the construction areas.

Middlebury-Starksboro VT 116

Middlebury-Starksboro VT 116

 The following is the anticipated work schedule for the week beginning Monday, May 07, 2018:

All work this week will be between East Middlebury/Middlebury to Bristol

  • Widening shoulders continues north to Quarry Road both northbound and southbound on VT 116
  • Milling continues
  • Ditch work continues

Motorists should expect delays as traffic control will be present allowing for one-way alternating traffic within the areas of construction activities.

 

 