Current Road Work

COUNT ON IT BUSINESS SERVICES, INC. works for several road/bridge contractors on projects in Southern Vermont providing Public Relations on specific projects.
Below is a list of current projects we now are working on.

Bridge #8 Update

Written by on September 13, 2018 in BRIDGE 8 VT ROUTE 17

This project is complete for the 2018 season.

In 2019, the contractor will be back to complete the fishing access, at which time I will notify you.

The following is the anticipated schedule for Bridge #8:

Written by on September 6, 2018 in BRIDGE 8 VT ROUTE 17

For the week beginning Monday, September 10, 2018:

  • There will be no work scheduled on this project until further notice.

 

The following is the anticipated schedule for Bridge #8:

Written by on August 30, 2018 in BRIDGE 8 VT ROUTE 17

For the week beginning Monday, September 03, 2018:

Monday thru Friday:

  • Continued removal of old concrete pier
  • Continue removal of causeway
  • General cleanup work throughout

 Motorists should expect minimal delays!

The following is the anticipated schedule for Bridge #8:

Written by on August 23, 2018 in BRIDGE 8 VT ROUTE 17

For the week beginning Monday, August 27, 2018:

Monday thru Friday:

  • Continued removal of old concrete pier
  • If time allows, begin causeway removal
  • General cleanup work throughout 

There should be minimal impact on traffic.

The following is the anticipated schedule for Bridge #8:

Written by on August 16, 2018 in BRIDGE 8 VT ROUTE 17
The following is the anticipated schedule for Bridge #8:

For the week beginning Monday, August 20, 2018:

Monday thru Friday:

  • Continued removal of old concrete pier
  • If time allows, begin causeway removal
  • General cleanup work throughout 

There should be minimal impact on traffic.

New Bridge #8

The following is the anticipated schedule for Bridge #8:

Written by on August 9, 2018 in BRIDGE 8 VT ROUTE 17

For the week beginning Monday, August 13, 2018:

 Monday thru Friday:

  • Continued removal of old concrete piers
  • Installation of bridge plug joints on both ends of the bridge
  • General cleanup work throughout

 

Motorists should be aware of traffic control allowing for one lane of alternating traffic.

The following is the anticipated schedule for Bridge #8:

Written by on August 2, 2018 in BRIDGE 8 VT ROUTE 17

For the week beginning Monday, August 06, 2018:

 Monday thru Friday:

  • Removal of old concrete piers
  • Installation of bridge plug joints
  • General cleanup work throughout

Motorists should be aware on Monday there will be traffic control allowing for one lane of alternating traffic.

There will be 2 lanes of traffic open during Addison County Field Days.

Bridge #8 – VT 117

Written by on July 28, 2018 in BRIDGE 8 VT ROUTE 17
Bridge #8 – VT 117

THE BRIDGE IS NOW OPEN TO THRU TRAFFIC.

Motorists should be aware of traffic control during the work week allowing for one-lane of alternating travel thru the construction area.

The following is the anticipated schedule for Bridge #8:

Written by on July 26, 2018 in BRIDGE 8 VT ROUTE 17
The following is the anticipated schedule for Bridge #8:

Paved Bridge#8 Deck

Weather permitting, Bridge #8 will be opened to thru traffic tomorrow, July 27, 2018.

 

The following is the anticipated work schedule for the week beginning Monday, July 30, 2018.

 Monday thru Sunday:

  •  Miscellaneous clean-up work.

 

Traffic control will be present during the daytime hours allowing for one-lane of alternating traffic over the bridge site.

The bridge was opened to traffic on/before the anticipated schedule!

The following is the anticipated schedule for Bridge #8:

Written by on July 19, 2018 in BRIDGE 8 VT ROUTE 17

The following is the anticipated work schedule for the week beginning Monday, July 22, 2018.  

 Monday thru Sunday:

  • Completion of the roadway approaches to the bridge.
  • Paving of the bridge deck
  • Installation of bridge rail & guardrail

This project remains on schedule!

Top