BRIDGE 8 VT ROUTE 17

The Vermont Agency of Transportation (VTrans) in conjunction with CCS Constructors, Inc. will be replacing Bridge 8 on VT Route 17 over the Otter Creek in New Haven, Vermont.  The new bridge that will be slightly longer and include two 11’ travel lanes with 4’ shoulders on each side.  Also included in this bridge replacement project will be a new fishing access northwest of the bridge.  This fishing access will include parking and a boat launch.

Click here for a complete Project Overview

Missed the public informational meeting Click here:  Bridge 8

Anyone with questions/concerns regarding the project may contact Stephanie Barrett, Public Outreach Coordinator at 802-862-6085 throughout the project.

If you would like to receive a weekly update of the contractors anticipated work schedule please email [email protected] your request.

The following is the anticipated schedule for Bridge #8:

Written by on July 12, 2018 in BRIDGE 8 VT ROUTE 17

For the week beginning Monday, July 16, 2018: 

Concrete is being placed on the bridge decking today, July 12, 2018.

 Monday thru Sunday:

  •  Continue building the roadway approaches to the bridge.

 

The following is the anticipated work schedule for Bridge #8:

Written by on July 5, 2018 in BRIDGE 8 VT ROUTE 17

For the week beginning Monday, July 09, 2018. 

 Monday thru Sunday:

  •  Continue preparation for placement of concrete deck.
  • Continued work on the east roadway approaches to the bridge.
  • Placement of the concrete deck for the later part of the week.

The contractor is on schedule.

 

The following is the anticipated work schedule on Bridge #8:

Written by on June 28, 2018 in BRIDGE 8 VT ROUTE 17
The following is the anticipated work schedule on Bridge #8:

For the week beginning Monday, July 02, 2018. 

The contractor will be working thru the Independence Day holiday in accordance with their schedule.

 

Monday thru Sunday:

  • Continue setting forms in preparation for placement of concrete deck.
  • Constructing new roadway approaches to the bridge.

Abutment

 

 

The following is the anticipated work schedule on Bridge #8:

Written by on June 21, 2018 in BRIDGE 8 VT ROUTE 17

For the week beginning Monday, June 25, 2018:

Monday thru Sunday:

  • Set forms to prepare for pouring concrete decking.

The following is the anticipated work schedule for Bridge #8 on VT 17

Written by on June 14, 2018 in BRIDGE 8 VT ROUTE 17
The following is the anticipated work schedule for Bridge #8 on VT 17

BRIDGE #8 ON VT ROUTE 17 REMAINS CLOSED TO TRAFFIC.

ALL motorists to follow the signed detour.

For the week beginning Monday, June 18, 2018:

Monday thru Sunday:

  • Structural steel to be set in place as the new precast abutments have been set.

Steel to be placed

East abutment

 

 

The following is the anticipated schedule for Bridge #8 on VT Route 17:

Written by on June 8, 2018 in BRIDGE 8 VT ROUTE 17

BRIDGE #8 ON VT ROUTE 17 IS CLOSED TO TRAFFIC.

ALL motorists to follow the signed detour.

 

The following is the anticipated work schedule for the week beginning Monday, June 11, 2018. 

It is anticipated the contractor will be working 7 days/week to get this project completed.

Monday thru Sunday:

  • Work continues on the removal of the existing bridge.

The following is the anticipated schedule for Bridge #8 on VT Route 17:

Written by on May 31, 2018 in BRIDGE 8 VT ROUTE 17

The following is the anticipated work schedule for the week beginning Monday, June 04, 2018. 

It is anticipated the contractor will be working 7 days/week to get this project completed.

Monday – 6:00am:

  • BRIDGE WILL BE CLOSED TO THRU TRAFFIC. Newly installed signs will guide motorists along the detour.

Monday thru Sunday:

  • Removal of the existing bridge to begin.

The following is the anticipated schedule for Bridge #8 on VT Route 17:

Written by on May 24, 2018 in BRIDGE 8 VT ROUTE 17

For the week beginning May 28, 2018:

Monday:  – No work due to the Memorial Day Holiday!

Tuesday thru Friday:

  • Continued driving steel H piling that will be utilized to support the new structure while preparing for demolition of the existing bridge.

June 4, 2018 remains the anticipated closure date of the bridge.  Signs will be uncovered when the detour begins.

 

The anticipated schedule for the week beginning Monday, May 21, 2018:

Written by on May 17, 2018 in BRIDGE 8 VT ROUTE 17

Monday thru Friday:

  • Continued driving steel H piling that will be utilized to support the new structure while preparing for demolition of the existing bridge.

 Motorists should expect traffic control to be present allowing for one lane of alternating traffic.

  June 4, 2018 remains the anticipated closure date of the bridge.  Signs to be installed this week but will remain covered until the detour begins.   

The following is the anticipated schedule for Monday, May 14, 2018:

Written by on May 10, 2018 in BRIDGE 8 VT ROUTE 17

Monday thru Friday:

  •  Prep work begins for the June 4, 2018 anticipated closure of the bridge with a well signed detour planned.

 Motorists should expect traffic control to be present allowing for one lane of alternating traffic.

Top