Rockingham Bridges-I91
The Vermont Agency of Transportation in conjunction with the design/build team of Reed & Reed, Inc. will complete bridge replacement on the I-91 bridges #24S & 24N over the Williams River in Rockingham, VT. This project has an anticipated completion date of September 2021.
I-91 NORTHBOUND & SOUTHBOUND ARE REDUCED TO ONE LANE WITHIN THE CONSTRUCTION ZONE.
I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY!
PLEASE USE CAUTION!
Anyone with questions or concerns regarding the project may contact Stephanie Barrett, Public Relations Officer at 802-862-6085 or toll free at 866-602-6868.
Follow us on Facebook Follow us on Twitter (#91rockbridges) Live Traffic Camera
Below is the anticipated work schedule for the week beginning Monday, June 03, 2019:
Monday thru Friday:
- Preparation work for demolition of SB Pier #1.
- Work continues on SB Piers #2 & #3.
- Begin removal of the existing southbound bridge deck
- Installation of the southbound traffic control devises.
TUESDAY:
- 9:30am there will be a rolling roadblock for southbound motorists in preparation of opening the southbound crossover. Motorists can anticipate approximately a 20-minute delay in their travels. If time does not allow for all work to be completed within the 20 minutes, there will be another rolling roadblock at 11:00am for approximately another 20-minute delay.
TUESDAY THRU THURSDAY:
- EXIT 6 SOUTHBOUND OFF-RAMP WILL BE CLOSED AT 9:30am June 4, 2019 until the end of the workday June 6, 2019. Motorists will be detoured using Exit 7 Off-Ramp then follow the signed detour on Route 5 southbound. All trucks over 14’ high will follow a signed detoured using Route 11.
KEEP YOUR HEADS UP AND YOUR CELL PHONE DOWN!
Below is the anticipated work schedule for the week beginning Monday, May 27, 2019:
Monday:
No work due to the Memorial Day Holiday!
Tuesday thru Friday:
- Work continues on the installation of the southbound crossover to include paving, shoulders & line striping.
- Work continues on SB Piers #2 & #3.
- Prep work on the existing southbound bridge for start of demolition
- Installation of the southbound traffic control devises.
REMINDERS:
- JUNE 04, 2019 at 9:30am there will be a rolling roadblock for southbound motorists in preparation of opening the southbound crossover. Motorists can anticipate approximately a 20-minute delay in their travels. If time does not allow for all work to be completed within the 20 minutes, there will be another rolling roadblock at 11:00am for approximately another 20-minute delay.
- JUNE 4, 2019 THRU JUNE 6, 2019 the EXIT 6 SOUTHBOUND OFF-RAMP WILL BE CLOSED AT 9:30am June 4, 2019 until the end of the workday June 6, 2019. Motorists will be detoured using Exit 7 Off-Ramp then follow the signed detour on Route 5 southbound. All trucks over 14’ high will follow a signed detoured using Route 11.
KEEP YOUR HEADS UP AND YOUR CELL PHONE DOWN!
***** SOUTHBOUND CROSSOVER OPENING ****
TUESDAY, JUNE 04, 2019:
- Beginning at 9:30am there will be a rolling roadblock for southbound motorists in preparation of opening the southbound crossover. Motorists can anticipate approximately a 20-minute delay in their travels. If time does not allow for all work to be completed within the 20 minutes, there will be another rolling roadblock at 11:00am for approximately another 20-minute delay.
JUNE 4, 2019 THRU JUNE 6, 2019:
EXIT 6 SOUTHBOUND OFF-RAMP WILL BE CLOSED AT 9:30am June 4, 2019 until the end of the work day June 6, 2019. Motorists will be detoured using Exit 7 Off-Ramp then follow the signed detour on Route 5 southbound. All trucks over 14’ high will follow a signed detoured using Route 11.
NARROW LANES – USE CAUTION – REDUCE SPEED!
The following is the anticipated work schedule on the I-91 bridges for the week beginning Monday, May 20, 2019:
Monday thru Friday:
- Work continues on the installation of the southbound crossover to include paving, shoulders and guardrail work.
- Work continues on SB Pier #3.
- Continue work for the 2nd shaft placement on Pier #2.
- Continue installation of the southbound traffic control devises.
NARROW LANES – USE CAUTION – REDUCE SPEED!
The following is the anticipated work schedule on the I-91 bridges for the week beginning Monday, May 13, 2019:
Monday thru Friday:
- Work continues on the installation of the southbound crossover.
- Work continues on SB Pier #3.
- Placement of concrete for the 1st shaft section on Pier #2.
- Begin form work for the 2nd shaft placement on Pier #2.
- Installation of the southbound traffic control devises.
NARROW LANES – USE CAUTION – REDUCE SPEED!
The following is the anticipated work schedule on the I-91 bridges for the week beginning Monday, May 06, 2019:
Monday thru Friday:
- Work continues on the installation of the southbound crossover.
- Work continues on SB Pier #3.
- Continue work SB Pier #2 for placement of concrete footing and 1st shaft.
- Continue maintenance on traffic control devises.
NARROW LANES – USE CAUTION!
The following is the anticipated work schedule on the I-91 bridges for the week beginning Monday, April 29, 2019:
Monday thru Friday:
- Work begins on building the crossover to re-route all traffic onto the NB Bridge
- Work continues on SB Pier #3 to include placement of 2nd shaft
- Prep work for 1st placement of concrete at SB Pier #2
NARROW LANES – USE CAUTION!
Tomorrow, April 26, 2019 @ 6:30a.m.:
- Weather permitting, there will be a I-91 northbound rolling road block for line striping before northbound motorists will be directed onto one lane of the newly constructed bridge. Motorists can anticipate approximately a 25-minute delay in their travels. Southbound traffic will still travel over one lane of the existing southbound bridge until a crossover is built.
- I-91 Exit 6 northbound On-Ramp will be opened up within an hour after the rolling road block clears and traffic is back up to speed over to the new I-91 Northbound Bridge.
Please note: If weather does not permit this to happen then the rain date will be for Monday, April 29, 2019 @ 9:30a.m.
The following is the anticipated work schedule on the I-91 bridges for the week beginning Monday, April 22, 2019:
Monday thru Friday:
- I-91 Exit 6 northbound On-Ramp remains closed for the week during ramp reconstruction to its original grade. All motorists to follow the signed detoured on Route 5 north to the Exit 7 northbound On-Ramp. The ramp is anticipated to be opened up on April 26, 2019 at which time all traffic will be switched over to the new I-91 Northbound Bridge.
- Weather permitting, paving the NB Bridge approaches
- Guardrail installation on the NB Bridge approaches
- Pavement markings on the NB Bridge and approaches
- Installation of new NB traffic control devices
- Work continues on Pier #3 to include placement of 2nd shaft
- Continue to excavate and remove ledge at Pier #2 SB cofferdam
Friday – April 26, 2019:
- Weather permitting, there will be a northbound rolling road block as motorists are directed over the newly constructed northbound bridge. Motorists can anticipate approximately a 10-minute delay in their travels. The start of the road block will be listed in next week’s release.
I-91 NORTHBOUND & SOUTHBOUND IS REDUCED TO ONE LANE WITH NO SHOULDERS WITHIN THE CONSTRUCTION ZONE.
I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY!
PLEASE USE CAUTION!