Rockingham Bridges-I91
The Vermont Agency of Transportation in conjunction with the design/build team of Reed & Reed, Inc. will complete bridge replacement on the I-91 bridges #24S & 24N over the Williams River in Rockingham, VT. This project has an anticipated completion date of September 2021.
I-91 NORTHBOUND & SOUTHBOUND ARE REDUCED TO ONE LANE WITHIN THE CONSTRUCTION ZONE.
I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY!
PLEASE USE CAUTION!
Anyone with questions or concerns regarding the project may contact Stephanie Barrett, Public Relations Officer at 802-862-6085 or toll free at 866-602-6868.
Follow us on Facebook Follow us on Twitter (#91rockbridges) Live Traffic Camera
The following is the anticipated work schedule on the I-91 bridges for the week beginning Monday, April 15, 2019:
IMPORTANT NOTIFICATION
Monday thru Friday:
- 7 a.m. I-91 Exit 6 northbound On-Ramp will be closed for two weeks while the ramp is reconstructed to its original grade. All motorists will follow a signed detoured on Route 5 north to the Exit 7 northbound On-Ramp. The ramp is anticipated to be opened up on April 26, 2019 at which time all traffic will be switched over to the new I-91 Northbound Bridge.
- Fine grading of the NB Bridge approaches
- Grinding and fine grading of the NB Bridge approaches
- Weather permitting, paving the NB Bridge and approaches
- Continue to excavate and remove ledge at Pier #2 SB cofferdam
I-91 NORTHBOUND & SOUTHBOUND IS REDUCED TO ONE LANE WITH NO SHOULDERS WITHIN THE CONSTRUCTION ZONE.
I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY!
PLEASE USE CAUTION!
The following is the anticipated work schedule on the I-91 bridges for the week beginning Monday, April 08, 2019:
IMPORTANT NOTIFICATION
On Monday, April 15, 2019 at 7 a.m. we will be closing the I-91 Exit 6 northbound On-Ramp for two weeks while the ramp is reconstructed to its original grade. All motorists will follow a signed detoured on Route 5 north to the Exit 7 northbound On-Ramp. The ramp is anticipated to be opened up on April 26, 2019 at which time all traffic will be switched over to the new I-91 Northbound Bridge.
************************************************************************
Monday thru Friday:
- Preparation work for placement of concrete at Pier #3 southbound
- Continue to excavate and remove ledge at Pier #2 SB cofferdam
- Grinding and fine grading of the NB Bridge approaches
- Continue installation of concrete curb on the bridge corners
- Continue maintenance of traffic control devices, due to weather
I-91 NORTHBOUND & SOUTHBOUND IS REDUCED TO ONE LANE WITH NO SHOULDERS WITHIN THE CONSTRUCTION ZONE.
I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY!
PLEASE USE CAUTION!
The following is the anticipated work schedule on the I-91 bridges for the week beginning Monday, April 01, 2019:
********************* IMPORTANT NOTIFICATION *********************
On Monday, April 15, 2019 at 7 a.m. we will be closing the I-91 Exit 6 northbound On-Ramp for two weeks while the ramp is reconstructed to its original grade. All motorists will follow a signed detoured on Route 5 north to the Exit 7 northbound On-Ramp. The ramp is anticipated to be opened up on April 26, 2019 at which time all traffic will be switched over to the new I-91 Northbound Bridge.
************************************************************************
Monday thru Friday
- Continue form work for Pier #3 southbound footing
- Continue to excavate and remove ledge at Pier #2 SB cofferdam
- Continue various items for the completion of the NB Bridge to include the installation of the deck membrane and concrete curb on the bridge corners
- Continue maintenance of traffic control devices, due to weather
I-91 NORTHBOUND & SOUTHBOUND IS REDUCED TO ONE LANE WITH NO SHOULDERS WITHIN THE CONSTRUCTION ZONE.
I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY!
PLEASE USE CAUTION!
The following is the anticipated work schedule on the I-91 bridges for the week beginning Monday, March 25, 2019:
Monday thru Friday:
- Begin form work for Pier #3 southbound footing
- Complete install of “Sheet Pile” at Pier #2 SB for ground stabilization
- Excavation and ledge removal at Pier #2 SB cofferdam
- Continue various items for the completion of the NB Bridge to include placement of curb
- Continue maintenance of traffic control devices, due to weather
I-91 NORTHBOUND & SOUTHBOUND IS REDUCED TO ONE LANE WITH NO SHOULDERS WITHIN THE CONSTRUCTION ZONE.
I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY!
PLEASE USE CAUTION!
The following is the anticipated work schedule on the I-91 bridges for the week beginning Monday, March 18, 2019:
Monday thru Friday:
- Continue driving “H-Pile” at Pier #3 southbound
- Continue driving “Sheet Pile” at Pier #2 southbound for ground stabilization
- Continue installation of hangers & conduit under the NB Bridge
- Continue maintenance of traffic control devices, due to weather
I-91 NORTHBOUND & SOUTHBOUND IS REDUCED TO ONE LANE WITH NO SHOULDERS WITHIN THE CONSTRUCTION ZONE.
I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY!
PLEASE USE CAUTION!
The following is the anticipated work schedule on the I-91 bridges for the week beginning Monday, March 11, 2019:
Monday thru Friday:
- Continue driving “H-Pile” at Pier #3 southbound
- Continue driving “Sheet Pile” at Pier #2 southbound for ground stabilization
- Continue installation of hangers & conduit under the NB Bridge
- Continue maintenance of traffic control devices, due to weather
I-91 NORTHBOUND & SOUTHBOUND IS REDUCED TO ONE LANE WITH NO SHOULDERS WITHIN THE CONSTRUCTION ZONE.
I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY!
PLEASE USE CAUTION!
The following is the anticipated work schedule on the I-91 bridges for the week beginning Monday, March 04, 2019:
Monday thru Friday:
- Continue driving “H-Pile” at Pier #3 for ground stabilization
- Continue driving “Sheet Pile” at Pier #2 for ground stabilization
- Continue installation of hangers & conduit under the NB Bridge
- Continue maintenance of traffic control devices, due to weather
I-91 NORTHBOUND & SOUTHBOUND IS REDUCED TO ONE LANE WITH NO SHOULDERS WITHIN THE CONSTRUCTION ZONE.
I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY!
PLEASE USE CAUTION!
The following is the anticipated work schedule on the I-91 bridges for the week beginning Monday, February 25, 2019:
Monday thru Friday:
- Begin driving “H-Pile” at Pier #3 for ground stabilization
- Begin driving “Sheet Pile” at Pier #2 for ground stabilization
- Continue installation of hangers & conduit under the NB Bridge
- Continue maintenance of traffic control devices, due to weather
I-91 NORTHBOUND & SOUTHBOUND IS REDUCED TO ONE LANE WITH NO SHOULDERS WITHIN THE CONSTRUCTION ZONE.
I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY!
PLEASE USE CAUTION!
The following is the anticipated work schedule on the I-91 bridges for the week beginning Monday, February 18, 2019:
Monday thru Friday:
- Excavate for the southbound Pier #3 cofferdam
- Continue installation of conduit under the NB Bridge
- Continue drilling ledge for installation of southbound Pier #2 cofferdam
- Excavate at Pier #2 cofferdam to prep for sheet pile installation
- Continue maintenance of traffic control devices, due to weather
I-91 NORTHBOUND & SOUTHBOUND IS REDUCED TO ONE LANE WITH NO SHOULDERS WITHIN THE CONSTRUCTION ZONE.
I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY!
PLEASE USE CAUTION!