Rockingham Bridges-I91

The Vermont Agency of Transportation in conjunction with the design/build team of Reed & Reed, Inc. will complete bridge replacement on the I-91 bridges #24S & 24N over the Williams River in Rockingham, VT. This project has an anticipated completion date of September 2021.

I-91 NORTHBOUND & SOUTHBOUND ARE REDUCED TO ONE LANE WITHIN THE CONSTRUCTION ZONE.


I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY! 

PLEASE USE CAUTION!


Anyone with questions or concerns regarding the project may contact Stephanie Barrett, Public Relations Officer at 802-862-6085 or toll free at 866-602-6868.

Follow us on Facebook    Follow us on Twitter (#91rockbridges)  Live Traffic Camera

Facebook Logo

Rockingham Bridges I-91

Written by on November 29, 2018 in Rockingham Bridges-I91

The following is the anticipated work schedule for the week beginning Monday, December 03, 2018:

********* IMPORTANT NOTIFICATION *********

Due to the unfortunate timing of winter rolling in, we will not be able to complete the driving surface of the northbound bridge this 2018 construction season, as anticipated.  The traffic pattern will remain as it has been during the construction of the northbound bridge until Spring 2019 when the temperatures allow for paving the new bridge deck and approaches. 

Construction activities will continue thru the winter and I will continue sending you notifications unless otherwise stated.

************************************************

I-91 northbound bridge activities:

Monday thru Friday – 7:00am to 5:00pm:

  • Continue placement of the concrete barriers on the bridge.
  • Continue maintenance of traffic control devices, due to weather


I-91 NORTHBOUND & SOUTHBOUND IS REDUCED TO ONE LANE WITH NO SHOULDERS WITHIN THE CONSTRUCTION ZONE.

I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY!
PLEASE USE CAUTION!

Rockingham Bridges I-91

Written by on November 21, 2018 in Rockingham Bridges-I91

The following is the anticipated work schedule for the week beginning Monday, November 26, 2018:

********* IMPORTANT NOTIFICATION *********

Due to the unfortunate timing of winter rolling in, we will not be able to complete the driving surface of the northbound bridge this 2018 construction season, as anticipated.  The traffic pattern will remain as it has been during the construction of the northbound bridge until Spring 2019 when the temperatures allow for paving the new bridge deck and approaches. 

Construction activities will continue thru the winter and I will continue sending you notifications unless otherwise stated.

************************************************

I-91 northbound bridge activities:

Monday thru Thursday – 5:00pm to 5:00am
Monday thru Friday – 7:00am to 5:00pm:

  • Continue placement of the concrete barriers on the bridge.
  • Continue maintenance of traffic control devices, due to weather


I-91 NORTHBOUND & SOUTHBOUND IS REDUCED TO ONE LANE WITH NO SHOULDERS WITHIN THE CONSTRUCTION ZONE.

I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY!
PLEASE USE CAUTION!

Rockingham Bridges I-91

Written by on November 15, 2018 in Rockingham Bridges-I91

The following is the anticipated work schedule for the week beginning Sunday, November 18, 2018:

I-91 northbound bridge activities:

Sunday thru Tuesday – 5:00pm to 5:00am
Monday thru Wednesday – 7:00am to 5:00pm:

  • Continue work on both bridge approaches.
  • Continue placement of the concrete barriers on the bridge.

Thursday & Friday:

  • No work due to the Thanksgiving Day holiday.


I-91 NORTHBOUND & SOUTHBOUND IS REDUCED TO ONE LANE WITH NO SHOULDERS WITHIN THE CONSTRUCTION ZONE.

I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY!
PLEASE USE CAUTION!

Rockingham Bridges I-91

Written by on November 8, 2018 in Rockingham Bridges-I91

The following is the anticipated work schedule for the week beginning Monday, November 12, 2018:

I-91 northbound bridge activities:

Monday thru Thursday – 5:00pm to 5:00am
Monday thru Friday – 7:00am to 5:00pm:

  • Continue work on both bridge approaches.
  • Continue placement of the concrete barriers on the bridge.


I-91 NORTHBOUND & SOUTHBOUND IS REDUCED TO ONE LANE WITH NO SHOULDERS WITHIN THE CONSTRUCTION ZONE.

I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY!
PLEASE USE CAUTION!

Rockingham Bridges I-91

Written by on November 1, 2018 in Rockingham Bridges-I91

The following is the anticipated work schedule for the week beginning Monday, November 05, 2018:

I-91 northbound bridge activities:

Monday thru Thursday – 5:00pm to 5:00am
Monday thru Friday – 7:00am to 5:00pm:

  • Continue work on both approaches.
  • Continue curing of the concrete deck placements.
  • Continue placement of the barrier curb.

Please use caution while traveling thru the work zone.

Rockingham Bridges I-91

Written by on October 25, 2018 in Rockingham Bridges-I91
Rockingham Bridges I-91

The following is the anticipated work schedule for the week beginning Monday, October 29, 2018:

I-91 northbound bridge activities:

Monday thru Thursday – 5:00pm to 5:00am
Monday thru Friday – Daytime:

  • Continue work on both approaches.
  • Continue curing of the concrete deck placements.
  • Continue placement of the barrier curb.

Please use caution while traveling thru the work zone.

Curing Concrete

Curing Concrete

Rockingham Bridges I-91

Written by on October 18, 2018 in Rockingham Bridges-I91

The following is the anticipated work schedule for the week beginning Monday, October 22, 2018:

I-91 northbound bridge activities:

Monday thru Thursday – 5:00pm to 5:00am
Monday thru Friday – Daytime:

• Complete placing concrete deck segments.
• Complete approach road work up to the approach slab area.
• Continue work on approaches.
• Continue placement of the barrier curb.

Please use caution while traveling thru the work zone.

Rockingham Bridges I-91

Written by on October 11, 2018 in Rockingham Bridges-I91

The following is the anticipated work schedule for the week beginning Monday, October 15, 2018:

I-91 northbound bridge activities:        

Monday thru Thursday – 5:00pm to
Monday thru Friday – Daytime:

  • Continue placing concrete deck segments.
  • Complete installation deck reinforcing.
  • Complete approach road work up to the approach slab area.
  • Begin forming the approach slabs.
  • Begin installation of reinforcement for the barrier curb.

Please drive slow and use caution while traveling thru the work zone.

Rockingham Bridges I-91

Written by on October 4, 2018 in Rockingham Bridges-I91

The following is the anticipated work schedule for the week beginning Monday, October 08, 2018.

 I-91 northbound bridge activities:

Monday thru Thursday – 5:00pm to 5:00am
Monday thru Friday – Daytime:

  • Begin construction on the northbound abutment approach.
  • Begin placing concrete deck segments.
  • Continue installation deck reinforcing.
  • Complete forming back wall at the southern abutment.

Please drive slow and use caution while traveling thru the construction zone.

Rockingham Bridges I-91

Written by on September 27, 2018 in Rockingham Bridges-I91
The following is the anticipated work schedule for the week beginning Monday, October 01, 2018.
 
I-91 northbound bridge activities:
Monday thru Thursday – 5:00pm to 5:00am
Monday thru Friday – Daytime:
• Continue installation of bridge deck prep and overhang.
• Remove back wall forms at the northern abutment.
• Continue forming back wall at the southern abutment.
 
Please drive slow & use caution thru the work zone.