Rockingham Bridges-I91

The Vermont Agency of Transportation in conjunction with the design/build team of Reed & Reed, Inc. will complete bridge replacement on the I-91 bridges #24S & 24N over the Williams River in Rockingham, VT. This project has an anticipated completion date of September 2021.

I-91 NORTHBOUND & SOUTHBOUND ARE REDUCED TO ONE LANE WITHIN THE CONSTRUCTION ZONE.


I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY! 

PLEASE USE CAUTION!


Anyone with questions or concerns regarding the project may contact Stephanie Barrett, Public Relations Officer at 802-862-6085 or toll free at 866-602-6868.

Follow us on Facebook    Follow us on Twitter (#91rockbridges)  Live Traffic Camera

Facebook Logo

The anticipated work schedule for the I-91 Rockingham Bridges

Written by on September 20, 2018 in Rockingham Bridges-I91

For the week beginning Monday, September 24 , 2018:

I-91 northbound bridge activities:

Monday thru Thursday – 5:00pm to 5:00am:
Monday thru Friday – Daytime:

  • Continue installation of bridge deck form work and overhang.
  • Begin installing deck steel reinforcement.
  • Complete removal of temporary supports that held the beams and forms.
  • Remove back wall forms at the northern abutment.
  • Begin forming back wall at the southern abutment.

REED & REED WILL CONTINUE WORKING A NIGHT SHIFT.

The anticipated work schedule for the I-91 Rockingham Bridges

Written by on September 13, 2018 in Rockingham Bridges-I91

For the week beginning Monday, September 17 , 2018:

I-91 northbound bridge activities:

Monday thru Thursday – 5:00pm to 5:00am:
Monday thru Friday – Daytime:

  • Continue installation of bridge deck form work and overhang.
  • Continue removal of temporary supports that held the beams and forms.
  • Continue forming back wall at the northern abutment.
  • Begin forming back wall at the southern abutment.

REED & REED WILL CONTINUE WORKING A NIGHT SHIFT.

The anticipated work schedule for the I-91 Rockingham Bridges:

Written by on September 6, 2018 in Rockingham Bridges-I91

For the week beginning Monday, September 10 , 2018:

I-91 northbound bridge activities:

Monday thru Thursday – 5:00pm to 5:00am:
Monday thru Friday – Daytime:

  • Continue installation of bridge deck form work and overhang.
  • Continue removal of temporary supports that held the beams and forms.
  • Begin forming back wall at the northern abutment.

REED & REED WILL CONTINUE WORKING A NIGHT SHIFT.

The anticipated schedule for the I-91 Rockingham Bridges

Written by on August 30, 2018 in Rockingham Bridges-I91

For the week beginning Monday, September 03, 2018:

Monday:  No work – Happy Labor Day!

Tuesday thru Thursday – 5:00pm to 5:00am
Tuesday thru Friday – Daytime:

  • Continue installation of overhang.
  • Continue installing the steel decking
  • Continue removal of temporary supports that held the beams.

The anticipated work schedule for the I-91 Rockingham Bridges:

Written by on August 23, 2018 in Rockingham Bridges-I91

For the week beginning Monday, August 27 , 2018:

I-91 northbound bridge activities:

Monday thru Thursday – 5:00pm to 5:00am:
Monday thru Friday – Daytime:

  • Continue installation of overhang.
  • Begin installing the steel decking
  • Begin removal of temporary supports that held the beams.

REED & REED WILL CONTINUE WORKING A NIGHT SHIFT.

The anticipated work schedule for the I-91 Rockingham Bridges:

Written by on August 16, 2018 in Rockingham Bridges-I91
The anticipated work schedule for the I-91 Rockingham Bridges:

For the week beginning Monday, August 20 , 2018:

I-91 northbound bridge activities:

Monday thru Thursday – 5:00pm to 5:00am:
Monday thru Friday – Daytime:

  • Continued preparation work on the set girders to include concrete pours in anticipation of pouring the new bridge decking.
  • Begin post tension process of the girders.
  • Begin installation of overhang brackets.

PLEASE NOTE REED & REED WILL NOW BE WORKING A NIGHT SHIFT.

The anticipated work schedule for the I-91 Rockingham Bridges:

Written by on August 9, 2018 in Rockingham Bridges-I91

For the week beginning Monday, August 13, 2018:

I-91 northbound bridge activities:

 Monday thru Friday:

  •  Continued preparation work on the set girders to include concrete pours in anticipation of pouring the new bridge decking.

The anticipated work schedule for the I-91 Rockingham Bridges:

Written by on August 2, 2018 in Rockingham Bridges-I91

For the week beginning Monday, August 06, 2018:

I-91 northbound bridge activities:

 Monday thru Friday:

  •  Continued preparation work on the set girders to include concrete pours in anticipation of pouring the new bridge decking.

 

The anticipated work schedule for the I-91 Rockingham Bridges:

Written by on July 26, 2018 in Rockingham Bridges-I91
The anticipated work schedule for the I-91 Rockingham Bridges:

NB concrete beams in place

For the week beginning Monday, July 30, 2018:

I-91 northbound bridge activities:

Monday thru Friday:

  • Continued preparation work on the set girders to include concrete closure pours.

 

The anticipated work schedule for the I-91 Rockingham Bridges:

Written by on July 19, 2018 in Rockingham Bridges-I91

For the week beginning Monday, July 23, 2018:

I-91 northbound bridge activities:

 Monday thru Friday:

 •  Continued preparation work on the set girders to include concrete pours.

 ALL ROLLING ROAD BLOCKS ARE COMPLETE AT THIS TIME.  MOTORISTS SHOULD NOT ENCOUNTER ANY CONSTRUCTION DELAYS.