Rockingham Bridges-I91

The Vermont Agency of Transportation in conjunction with the design/build team of Reed & Reed, Inc. will complete bridge replacement on the I-91 bridges #24S & 24N over the Williams River in Rockingham, VT. This project has an anticipated completion date of September 2021.

I-91 NORTHBOUND & SOUTHBOUND ARE REDUCED TO ONE LANE WITHIN THE CONSTRUCTION ZONE.


I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY! 

PLEASE USE CAUTION!


Anyone with questions or concerns regarding the project may contact Stephanie Barrett, Public Relations Officer at 802-862-6085 or toll free at 866-602-6868.

Follow us on Facebook    Follow us on Twitter (#91rockbridges)  Live Traffic Camera

Facebook Logo

The anticipated work schedule for the I-91 Rockingham Bridges:

Written by on July 12, 2018 in Rockingham Bridges-I91
The anticipated work schedule for the I-91 Rockingham Bridges:

Tomorrow, July 13, 2018 will be the last of the rolling road blocks for the northbound bridge.  The anticipated times are as follows:

  • Southbound:  approx.. 6:00am & 12:00pm for approx. 10 mins.
  • Northbound:  approx.  5:30am & 8:00am for approx.. 20 mins.(the 8:00am will include a repair to a pothole forming)

For the week beginning Monday, July 16, 2018:

 Monday thru Friday:

  • Preparation work on the set girders in anticipation of concrete.

The anticipated work schedule for I-91 Rockingham Bridges:

Written by on July 6, 2018 in Rockingham Bridges-I91

For the week beginning Monday, July 09, 2018:

I-91 northbound bridge activities:

 Monday:

  • Dismantle one crane to relocate (this may go into Tuesday)

 Tuesday thru Friday:

  • Complete beam erection with daily rolling road blocks see below
  • Truck traffic on Golden Hill Road

  I-91 APPROX. ROLLING ROAD BLOCK SCHEDULES for beam deliveries:

  • Southbound: . 7:30am & 12:00pm for approx. 10 mins.
  • Northbound:   8:30am & 2:00pm for approx.. 20 mins.

NOTE:  If all beams are set by Thursday afternoon there will not be any rolling road blocks for Friday.

Please note rolling road block times could vary due to unforeseen circumstances.

*  The northbound rolling road blocks also includes the Exit 6 on ramp.  Motorists may want to detour on Route 5 to use the Exit 7 on ramp in Springfield to avoid delays.

The following is the anticipated schedule for the I-91 Rockingham Bridges

Written by on June 29, 2018 in Rockingham Bridges-I91
The following is the anticipated schedule for the I-91 Rockingham Bridges

 

The schedule beginning Friday, June 29, 2018 thru Tuesday, July 3, 2018 @ noon:

I-91 northbound bridge activities:

  • Continued beam erection on Pier 1 and to Pier 2
  • Erect 16000lb crane to Abutment 1 – southbound
  • Truck traffic on Golden Hill Road

Work to resume on Monday, July 09, 2018.

I-91 APPROX. ROLLING ROAD BLOCK SCHEDULES for beam deliveries:
– Friday: Approx.. 5:00am southbound for approx. 10 mins. and approx. 6:30am northbound for approx. 20mins.
– Saturday: Approx. 2:30am & 4:00am southbound for approx. 10 mins. and approx. 3:15am & 7:30am northbound for approx. 20mins.
– Sunday: Approx.. 5:00am southbound for approx. 10 mins. and approx. 6:30am northbound for approx. 20mins.
– Monday: Approx. 2:30am & 4:00am southbound for approx. 10 mins. and approx. 3:15am & 7:30am northbound for approx. 20mins.
– Tuesday: Approx.. 5:00am southbound for approx. 10 mins. and approx. 6:30am northbound for approx. 20mins.

Please note rolling road block times could vary due to unforeseen circumstances.
* The northbound rolling road blocks also includes the Exit 6 on ramp. Motorists may want to detour on Route 5 to use the Exit 7 on ramp in Springfield to avoid delays.

The following is the anticipated schedule on the I-91 Rockingham Bridges:

Written by on June 21, 2018 in Rockingham Bridges-I91

For the week beginning Monday, June 25, 2018:

I-91 northbound bridge activities:

 Monday thru SUNDAY – Daytime:

 I-91 ROLLING ROAD BLOCKS  to allow for beam deliveries:

  • 2 daily southbound for approx.. 15 minutes
  • 2 daily northbound* for approx.. 30 minutes
  • Please note rolling road block times could vary due to avoidance of peak traffic flow and/or due to unforeseen circumstances.

 * The northbound rolling road blocks also include the Exit 6 on ramp.  Motorists may want to follow the detour on Route 5 to use the Exit 7 on ramp in Springfield to avoid delays.  Oversize trucks must follow their permitted route. 

  • Continued beam erection from Abutment 2 to Pier 2
  • Begin beam erection from Pier 1 to Pier 2
  • Complete backfilling Abutment 1
  • Truck traffic on Golden Hill Road

1st beam to northbound abutment

Written by on June 21, 2018 in Rockingham Bridges-I91, Uncategorized
1st beam to northbound abutment

The following in the anticipated schedule for the I-91 Rockingham Bridges

Written by on June 15, 2018 in Rockingham Bridges-I91

For the week beginning, June 18, 2018:

I-91 northbound bridge activities:

 Monday thru Friday – Daytime:

 I-91 ROLLING ROAD BLOCKS  to allow for beam deliveries:

At approx.. 8:00am and 11:00am southbound for approximately 30 minutes

At approx.. 10:00am and 2:00pm northbound* for approximately 30 minutes

Please note rolling road block times could vary due to unforeseen circumstances.

* The northbound rolling road blocks also include the Exit 6 on ramp.  Motorists may want to follow the detour on Route 5 to use the Exit 7 on ramp in Springfield to avoid delays.  Oversize trucks must follow their permitted route. 

  • Continued beam erection
  • Complete removing forms from Abutment 1
  • Cleanup of Abutment 1 and begin backfilling
  • Truck traffic on Golden Hill Road

 

 

The following is the anticipated schedule on the I-91 Rockingham Bridges:

Written by on June 8, 2018 in Rockingham Bridges-I91
The following is the anticipated schedule on the I-91 Rockingham Bridges:

For the week beginning Monday, June 11, 2018:

I-91 northbound bridge activities:

Daily I-91 ROLLING ROAD BLOCKS  to allow for beam deliveries:

At approx.. 8:00am and 11:00am southbound for approximately 30 minutes

At approx.. 10:00am and 2:00pm northbound* for approximately 30 minutes

Please note rolling road block times could vary due to unforeseen circumstances.

*  The northbound rolling road blocks also includes the Exit 6 on ramp.  Motorists may want to detour on Route 5 to use the Exit 7 on ramp in Springfield to avoid delays.

  • Continued beam erection
  • Complete Abutment 1 support walls and remove forms
  • Truck traffic on Golden Hill Road

 

The following is the anticipated schedule on the I-91 Rockingham Bridges:

Written by on June 1, 2018 in Rockingham Bridges-I91

For the week beginning Monday, June 4, 2018:

Monday thru Friday – Daytime:

  • Continued installing beam support hardware on Piers
  • Continue mobilizing cranes to needed locations
  • Continue receiving beams at the lay-down area
  • Continued preparation to begin beam erection to begin Thursday
  • Continued concrete work on Abutment 1 for support walls
  • Complete backfilling at abutment 2 and construct crane pad
  • Truck traffic on Golden Hill Road

Thursday – I-91 ROLLING ROAD BLOCKS  to allow for beam deliveries:

  • 8:00am and 11:00am southbound for approximately 30 minutes
  • 10:00am and 2:00pm northbound for approximately 30 minutes

 Friday – I-91 ROLLING ROAD BLOCKS  to allow for beam deliveries:

  • 8:00am southbound for approximately 30 minutes
  • 10:00am northbound for approximately 30 minutes

The following is the anticipated schedule on the I-91 Rockingham Bridges

Written by on May 24, 2018 in Rockingham Bridges-I91

Work on the northbound bridge for the week beginning Monday, May 28, 2018:

Monday:

  • No work due to the Memorial Day Holiday!

 Tuesday thru Friday – Daytime:

  • Complete installation of beam support towers for Piers 1, 2 & 3
  • Continued work on Abutment 1 footings & support wall
  • Mobilization of large erection cranes to trestle and abutment 2
  • Preparation to begin beam erection
  • Truck traffic on Golden Hill Road

The anticipated schedule for the week beginning Monday, May 21, 2018:

Written by on May 18, 2018 in Rockingham Bridges-I91

Monday, May 21, 2018 at 1:00pm there will be a short I-91 southbound rolling road block to allow for some minor bridge deck maintenance.

  • Continue work on girder erection support tower on Pier 1
  • Complete installation of beam support towers for Piers 2 & 3
  • Continued work on Abutment 1 footings
  • Continue moving trestle beams to accommodate for beam erection
  • Truck traffic on Golden Hill Road

 

Top