Rockingham Bridges-I91

The Vermont Agency of Transportation in conjunction with the design/build team of Reed & Reed, Inc. will complete bridge replacement on the I-91 bridges #24S & 24N over the Williams River in Rockingham, VT. This project has an anticipated completion date of September 2021.

I-91 NORTHBOUND & SOUTHBOUND ARE REDUCED TO ONE LANE WITHIN THE CONSTRUCTION ZONE.


I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY! 

PLEASE USE CAUTION!


Anyone with questions or concerns regarding the project may contact Stephanie Barrett, Public Relations Officer at 802-862-6085 or toll free at 866-602-6868.

Follow us on Facebook    Follow us on Twitter (#91rockbridges)  Live Traffic Camera

Facebook Logo

Rockingham Bridges I-91

Written by on November 25, 2020 in Rockingham Bridges-I91

The following is an update of the construction to take place for the week beginning Monday, November 30, 2020.

Monday through Friday:  6:00 a.m. to 5:00 p.m.:

  • Bridge deck work continues
  • Maintenance of traffic control devices continues

NARROW LANES  –  REDUCED SPEEDS  –  USE CAUTION!

Rockingham Bridges I-91

Written by on November 19, 2020 in Rockingham Bridges-I91
Rockingham Bridges I-91

The following is an update of the construction to take place for the week beginning Monday, November 23, 2020.

Monday through Friday:  6:00 a.m. to 5:00 p.m.:

  • Bridge deck work continues to include concrete slab pours
  • Maintenance of traffic control devices continues

NARROW LANES  –  REDUCED SPEEDS  –  USE CAUTION!

Rockingham Bridges I-91

Written by on November 12, 2020 in Rockingham Bridges-I91
Rockingham Bridges I-91

The following is an update of the construction to take place for the week beginning Monday, November 16, 2020.

Monday through Friday:  6:00 a.m. to 5:00 p.m.:

  • Bridge deck work continues to include concrete slab pours
  • Maintenance of traffic control devices continues

NARROW LANES  –  REDUCED SPEEDS  –  USE CAUTION!

Rockingham Bridges I-91

Written by on November 5, 2020 in Rockingham Bridges-I91

The following is an update of the construction to take place for the week beginning Monday, November 9, 2020.

Monday through Friday:  6:00 a.m. to 5:00 p.m.:

  • Bridge deck work continues to include tying in deck steel
  • Maintenance of traffic control devices continues

Tuesday 6:00 a.m. to 5:00 p.m.:

  • Placement of concrete deck at the south end of the bridge deck

NARROW LANES  –  REDUCED SPEEDS  –  USE CAUTION!

Rockingham Bridges I-91

Written by on October 30, 2020 in Rockingham Bridges-I91
Rockingham Bridges I-91

The following is an update of the construction to take place for the week beginning Saturday, October 30, 2020.

Saturday, Wednesday and Friday 6:00 a.m. to 5:00 p.m.:

  • Continue placement of concrete deck slabs

Monday through Friday:  6:00 a.m. to 5:00 p.m.:

  • Bridge deck work continues to include tying in deck steel
  • Maintenance of traffic control devices continues

NARROW LANES  –  REDUCED SPEEDS  –  USE CAUTION!

Rockingham Bridges I-91

Written by on October 22, 2020 in Rockingham Bridges-I91

The following is an update of the construction to take place for the week beginning Monday, October 26, 2020.

Monday through Friday:  6:00 a.m. to 5:00 p.m.:

  • Bridge deck work continues to include tying in deck steel
  • Potential concrete deck slab placement later in the week
  • Maintenance of traffic control devices continues

NARROW LANES  –  REDUCED SPEEDS  –  USE CAUTION!

Rockingham Bridges I-91

Written by on October 15, 2020 in Rockingham Bridges-I91
Rockingham Bridges I-91

The following is an update of the construction to take place for the week beginning Monday, October 19, 2020.

Tuesday – 9:00 a.m.

  • Scheduled Concrete pour for continued deck slab placement

Thursday – 9:00 a.m.:

  • Scheduled Concrete pour for continued deck slab placement

Monday through Friday:  6:00 a.m. to 5:00 p.m.:

  • Bridge deck work continues to include tying in deck steel
  • Maintenance of traffic control devices continues

NARROW LANES  –  REDUCED SPEEDS  –  USE CAUTION!

Rockingham Bridges I-91

Written by on October 8, 2020 in Rockingham Bridges-I91
Rockingham Bridges I-91

The following is an update of the construction to take place for the week beginning Monday, October 12, 2020.

Monday:

  • No work due to the Columbus Day holiday

Tuesday:

  • Approach slab work on the northbound abutment

Thursday:

  • Approach slab work on the southbound abutment

Tuesday through Friday:  6:00 a.m. to 5:00 p.m.:

  • Bridge deck work continues to include tying in deck steel along with the 1st concrete deck placement
  • Maintenance of traffic control devices continues

NARROW LANES  –  REDUCED SPEEDS  –  USE CAUTION!

Rockingham Bridges I-91

Written by on October 1, 2020 in Rockingham Bridges-I91
Rockingham Bridges I-91


The following is an update of the construction to take place for the week beginning Monday, October 5, 2020.

Monday through Friday:  6:00 a.m. to 5:00 p.m.:

  • Bridge deck work continues to include tying in deck steel
  • Maintenance of traffic control devices continues

NARROW LANES  –  REDUCED SPEEDS  –  USE CAUTION!

Rockingham Bridges I-91

Written by on October 1, 2020 in Rockingham Bridges-I91
Rockingham Bridges I-91


The following is an update of the construction to take place for the week beginning Monday, September 28, 2020.

Monday through Friday:  6:00 a.m. to 5:00 p.m.:

  • Bridge deck work continues to include tying in deck steel
  • Maintenance of traffic control devices continues

NARROW LANES  –  REDUCED SPEEDS  –  USE CAUTION!