Rockingham Bridges-I91

The Vermont Agency of Transportation in conjunction with the design/build team of Reed & Reed, Inc. will complete bridge replacement on the I-91 bridges #24S & 24N over the Williams River in Rockingham, VT. This project has an anticipated completion date of September 2021.

I-91 NORTHBOUND & SOUTHBOUND ARE REDUCED TO ONE LANE WITHIN THE CONSTRUCTION ZONE.


I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY! 

PLEASE USE CAUTION!


Anyone with questions or concerns regarding the project may contact Stephanie Barrett, Public Relations Officer at 802-862-6085 or toll free at 866-602-6868.

Follow us on Facebook    Follow us on Twitter (#91rockbridges)  Live Traffic Camera

Facebook Logo

Rockingham Bridges – I91

Written by on July 9, 2020 in Rockingham Bridges-I91
Rockingham Bridges – I91


The following is an update of the construction to take place for the week beginning Sunday, July 12, 2020.

Southbound I-91 bridge activities resume with limited personnel.

Sunday through Friday- 24 hours/day:

  • Bridge deck work to continue
  • Placement of concrete and other work at the northbound abutment
  • Tree branch trimming within the construction zone on I-91
  • Maintenance of traffic control devices continues

NARROW LANES – REDUCED SPEEDS – USE CAUTION!

Please Note: As part of Governor Scott’s “Work Smart, Stay Safe” order, all construction crews are currently subject to safety restrictions and precautions.

Rockingham Bridges – I91

Written by on July 2, 2020 in Rockingham Bridges-I91
Rockingham Bridges – I91


The following is an update of the construction to take place for the week beginning Monday, July 01, 2020.

Southbound I-91 bridge activities resume with limited personnel.

Monday through Friday- 24 hours/day:

  • Bridge deck work to continue
  • Maintenance of traffic control devices continues

NARROW LANES – REDUCED SPEEDS – USE CAUTION!

Please Note: As part of Governor Scott’s “Work Smart, Stay Safe” order, all construction crews are currently subject to safety restrictions and precautions.

Rockingham Bridges – I91

Written by on June 25, 2020 in Rockingham Bridges-I91
Rockingham Bridges – I91


The following is an update of the construction to take place for the week beginning Monday, June 29, 2020.

Southbound I-91 bridge activities resume with limited personnel.

Monday through Friday- 6:00 a.m. to 5:00 p.m.:

  • Bridge deck work to continue
  • Maintenance of traffic control devices continues

Please Note: As part of Governor Scott’s “Work Smart, Stay Safe” order, all construction crews are currently subject to safety restrictions and precautions.

NARROW LANES – REDUCED SPEEDS – USE CAUTION!

Rockingham Bridges – I91

Written by on June 18, 2020 in Rockingham Bridges-I91

The following is an update of the construction to take place for the week beginning Monday, June 22, 2020.

Southbound I-91 bridge activities resume with limited personnel.

Monday – 6:00 a.m. to noon:

Tuesday through Friday (Saturday, if necessary) – 2:00 a.m. until noon:

  • Bridge deck work to continue
  • Maintenance of traffic control devices continues

Please Note: As part of Governor Scott’s “Work Smart, Stay Safe” order, all construction crews are currently subject to safety restrictions and precautions.

NARROW LANES – REDUCED SPEEDS – USE CAUTION!

Rockingham Bridges – I91

Written by on June 11, 2020 in Rockingham Bridges-I91

The following is an update of the construction to take place for the week beginning Monday, June 15, 2020.

Southbound I-91 bridge activities resume with limited personnel.

Monday through Friday:

  • Continue bridge deck work
  • Demolition work the old Pier 3 footing
  • Prep work at Abutment 2
  • Continue maintenance of traffic control devises

MONDAY, JUNE 11, 2020 – ROLLING ROAD BLOCKS:

Due to some necessary roadway maintenance, Beginning at Exit 5 northbound, motorists can expect a rolling road block beginning at 8:00 a.m. with another at 10:00 a.m., if necessary, causing approximately a 20-minute delay. 

Beginning at Exit 7 southbound, motorists can expect a rolling road block beginning at 12:30 p.m. with another at 1:30 p.m., if necessary, causing approximately a 20-minute delay.

Please Note: As part of Governor Scott’s “Work Smart, Stay Safe” order, all construction crews are currently subject to safety restrictions and precautions.

NARROW LANES – REDUCED SPEEDS – USE CAUTION!

Rockingham Bridges – I91

Written by on June 4, 2020 in Rockingham Bridges-I91

The following is an update of the construction to take place for the week beginning Monday, June 08, 2020.

Southbound I-91 bridge activities resume with limited personnel.

Monday through Friday:

  • Continue bridge deck work
  • Continue maintenance of traffic control devises

THURSDAY, JUNE 11, 2020 – ROLLING ROAD BLOCKS:

Due to some necessary roadway maintenance, Beginning at Exit 5 northbound, motorists can expect a rolling road block beginning at 8:00 a.m. with another at 10:00 a.m., if necessary, causing approximately a 20-minute delay. 

Beginning at Exit 7 southbound, motorists can expect a rolling road block beginning at 12:30 p.m. with another at 1:30 p.m., if necessary, causing approximately a 20-minute delay.

Please Note: As part of Governor Scott’s “Work Smart, Stay Safe” order, all construction crews are currently subject to safety restrictions and precautions.

NARROW LANES – REDUCED SPEEDS – USE CAUTION!

Rockingham Bridges I-91

Written by on May 28, 2020 in Rockingham Bridges-I91

The following is an update of the construction to take place for the week beginning Monday, June 01, 2020.

Southbound I-91 bridge activities resume with limited personnel.

Monday through Friday:

  • Work on Pier’s 2 and 3
  • Continue bridge deck work
  • Continue maintenance of traffic control devises

Please Note: As part of Governor Scott’s “Work Smart, Stay Safe” order, all construction crews are currently subject to safety restrictions and precautions.

NARROW LANES – REDUCED SPEEDS – USE CAUTION!

Rockingham Bridges I-91

Written by on May 21, 2020 in Rockingham Bridges-I91

The following is an update of the construction to take place for the week beginning Tuesday, May 26, 2020.

Southbound I-91 bridge activities resume with limited personnel.

Monday:  No work due to the Memorial Day holiday

Tuesday through Friday:

  • Work on Pier’s 1 and 2
  • Bridge deck work
  • Continue maintenance of traffic control devises

Please Note: As part of Governor Scott’s “Work Smart, Stay Safe” order, all construction crews are currently subject to safety restrictions and precautions.

NARROW LANES – REDUCED SPEEDS – USE CAUTION!

Rockingham Bridges I-91

Written by on March 12, 2020 in Rockingham Bridges-I91

The following is an update of the construction to take place for the week beginning Monday, March 16, 2020.

Southbound I-91 bridge activities will be suspended after work tomorrow Friday, March 13, 2020 as the contractor will be shutting down until mid-April for the final phase of construction.  Minimal personnel will continue to be onsite during this shut-down period.I will resume these weekly updates prior to work resuming in full capacity.

NARROW LANES – REDUCED SPEEDS – USE CAUTION!

Rockingham Bridges I-91

Written by on March 5, 2020 in Rockingham Bridges-I91

The following is an update of the construction to take place for the week beginning Monday, March 9, 2020.

Southbound I-91 bridge activities:

Monday through Friday:

  • Continue girder closures
  • Mobilization of equipment to Golden Hill Road
  • Continue maintenance of traffic control devises

NARROW LANES – REDUCED SPEEDS – USE CAUTION!

Top