Rockingham Bridges-I91
The Vermont Agency of Transportation in conjunction with the design/build team of Reed & Reed, Inc. will complete bridge replacement on the I-91 bridges #24S & 24N over the Williams River in Rockingham, VT. This project has an anticipated completion date of September 2021.
I-91 NORTHBOUND & SOUTHBOUND ARE REDUCED TO ONE LANE WITHIN THE CONSTRUCTION ZONE.
I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY!
PLEASE USE CAUTION!
Anyone with questions or concerns regarding the project may contact Stephanie Barrett, Public Relations Officer at 802-862-6085 or toll free at 866-602-6868.
Follow us on Facebook Follow us on Twitter (#91rockbridges) Live Traffic Camera
The following is an update of the construction to take place for the week beginning Monday, March 2 2020.
Southbound I-91 bridge activities:
Monday through Friday:
- Continue girder closures
- Continue work on abutments
- Continue work on the pier footers
- Continue maintenance of traffic control devises
NARROW LANES – REDUCED SPEEDS – USE CAUTION!
The following is an update of the construction to take place for the week beginning Monday, February 24, 2020.
Southbound I-91 bridge activities:
Saturday (weather permitting), Monday through Friday:
- Continue girder closures
- Continue work on abutments
- Continue work on the pier footers
- Continue maintenance of traffic control devises
NARROW LANES – REDUCED SPEEDS – USE CAUTION!
The following is an update of the construction to take place for the week beginning Saturday, February 15, 2020.
Southbound I-91 bridge activities:
Saturday (weather permitting), Monday through Friday:
- Continue girder closures
- Demolition of the old northbound Pier 2 footer
- Continue maintenance of traffic control devises
NARROW LANES – REDUCED SPEEDS – USE CAUTION!
The following is an update of the construction to take place for the week beginning Saturday, February 8, 2020.
Southbound I-91 bridge activities:
Saturday (weather permitting), Monday through Friday:
- Continue girder closures
- Demolition of the old northbound Pier 2 footer
- Continue maintenance of traffic control devises
NARROW LANES – REDUCED SPEEDS – USE CAUTION!
The following is an update of the construction to take place for the week beginning Saturday, February 1, 2020.
Southbound I-91 bridge activities:
Saturday (weather permitting), Monday through Friday:
- Continue girder closures
- Continue maintenance of traffic control devises
NARROW LANES – REDUCED SPEEDS – USE CAUTION!
The following is an update of the construction to take place for the week beginning Saturday, January 25, 2020.
Southbound I-91 bridge activities:
Saturday (weather permitting), Monday through Friday:
- Continue girder closures
- Continue demolition of remaining old northbound pier footings
- Continue maintenance of traffic control devises
NARROW LANES – REDUCED SPEEDS – USE CAUTION!
The following is an update of the construction to take place for the week beginning Saturday, January 18, 2020.
Southbound I-91 bridge activities:
Monday through Friday:
- Continue girder closures
- Continue demolition of remaining old northbound pier footings
- Continue maintenance of traffic control devises
NARROW LANES – REDUCED SPEEDS – USE CAUTION!
The following is an update of the construction to take place for the week beginning Saturday, January 11, 2020.
Southbound I-91 bridge activities:
Monday through Friday:
- Continue girder closures
- Demolition of remaining old northbound pier footings
- Continue maintenance of traffic control devises
NOTE: The scheduled rolling road blocks are complete as all the girders have been erected.
NARROW LANES – REDUCED SPEEDS – USE CAUTION!
The following is an update of the construction to take place for the week beginning Monday, January 06, 2020.
Southbound I-91 bridge activities:
Monday through Friday:
- Weather permitting, continue girder erection
- Continue work on girder closures
- Continue maintenance of traffic control devises
Weather permitting, beginning at Exit 7 southbound, motorists can expect two daily rolling roadblocks between the hours of 8:00am and 4:00pm causing approximately a 30-minute delay.
NARROW LANES – REDUCED SPEEDS – USE CAUTION!
The following is an update of the construction to take place for the week beginning Monday, December 30, 2019.
Southbound I-91 bridge activities:
Monday through Friday:
- Weather permitting, continue girder erection
- Continue maintenance of traffic control devises
Weather permitting, beginning at Exit 7 southbound, motorists can expect two daily rolling roadblocks between the hours of 8:00am and 4:00pm causing approximately a 30-minute delay.
NARROW LANES – REDUCED SPEEDS – USE CAUTION!