Rockingham Bridges-I91

The Vermont Agency of Transportation in conjunction with the design/build team of Reed & Reed, Inc. will complete bridge replacement on the I-91 bridges #24S & 24N over the Williams River in Rockingham, VT. This project has an anticipated completion date of September 2021.

I-91 NORTHBOUND & SOUTHBOUND ARE REDUCED TO ONE LANE WITHIN THE CONSTRUCTION ZONE.


I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY! 

PLEASE USE CAUTION!


Anyone with questions or concerns regarding the project may contact Stephanie Barrett, Public Relations Officer at 802-862-6085 or toll free at 866-602-6868.

Follow us on Facebook    Follow us on Twitter (#91rockbridges)  Live Traffic Camera

Facebook Logo

Rockingham Bridges I-91

Written by on December 19, 2019 in Rockingham Bridges-I91

The following is an update of the construction to take place for the week beginning Monday, December 23, 2019.

Southbound I-91 bridge activities:

Monday through Friday:

  • No work due to the Christmas holiday
  • Work continues on the southbound abutment (#1) approach
  • Girder prep work at the southbound weigh station north of the bridge
  • Continue maintenance of traffic control devices

Please note there will be girders delivered onto the project site.

NARROW LANES – REDUCED SPEEDS – USE CAUTION!

Rockingham Bridges I-91

Written by on December 12, 2019 in Rockingham Bridges-I91

The following is an update of the construction to take place for the week beginning Monday, December 16, 2019.

Southbound I-91 bridge activities:

Monday through Friday:

  • Weather permitting, continue girder erection
  • Work continues on the southbound abutment (#1) approach
  • Girder prep work at the southbound weigh station north of the bridge
  • Continue maintenance of traffic control devices

Weather permitting, beginning at Exit 7 southbound, motorists can expect two daily rolling roadblocks between the hours of 8:00am and 4:00pm causing approximately a 30-minute delay.

NARROW LANES – REDUCED SPEEDS – USE CAUTION!

Rockingham Bridges I-91

Written by on December 5, 2019 in Rockingham Bridges-I91
Rockingham Bridges I-91

The following is an update of the construction to take place for the week beginning Monday, December 9, 2019.

Southbound I-91 bridge activities:

Monday through Friday:

  • Weather permitting, continue girder erection
  • Continue work on Pier 1
  • Work continues on the southbound abutment (#1) approach
  • Work continues on the northbound abutment (#2) approach
  • Continue maintenance of traffic control devises

Weather permitting, beginning at Exit 7 southbound, motorists can expect two daily rolling roadblocks between the hours of 8:00am and 4:00pm causing approximately a 30-minute delay.

NARROW LANES – REDUCED SPEEDS – USE CAUTION!

Rockingham Bridges I-91

Written by on November 27, 2019 in Rockingham Bridges-I91

The following is an update of the construction to take place for the week beginning Monday, December 2, 2019.

Southbound I-91 bridge activities:

Monday through Friday:

  • Weather permitting, continue girder erection
  • Continue work on Pier 1
  • Work continues on the southbound abutment (#1) approach
  • Work continues on the northbound abutment (#2) approach

Weather permitting, beginning at Exit 7 southbound, motorists can expect two daily rolling roadblocks between the hours of 8:00am and 4:00pm causing approximately a 30-minute delay.

NARROW LANES – REDUCED SPEEDS – USE CAUTION!

Rockingham Bridges I-91

Written by on November 21, 2019 in Rockingham Bridges-I91
Rockingham Bridges I-91

The following is an update of the construction to take place for the week beginning Monday, November 25, 2019.

Southbound I-91 bridge activities:

Monday through Wednesday @ noon:

  • Continue work on Pier 1
  • Work continues on the southbound abutment (#1) approach
  • Weather permitting, continue girder erection
  • Continue maintenance of traffic control devises

Thursday & Friday: 

  • No work due to the Thanksgiving Day holiday!

Weather permitting, beginning at Exit 7 southbound, motorists can expect two daily rolling roadblocks between the hours of 8:00am and 4:00pm causing approximately a 30-minute delay.

NARROW LANES – REDUCED SPEEDS – USE CAUTION!

Rockingham Bridges I-91

Written by on November 14, 2019 in Rockingham Bridges-I91
Rockingham Bridges I-91

The following is an update of the construction to take place for the week beginning Monday, November 18, 2019.

Southbound I-91 bridge activities:

Monday through Friday:

  • Continue work on Pier 1
  • Work continues on the southbound abutment (#1) approach
  • Weather permitting, continue girder erection
  • Continue maintenance of traffic control devises

Weather permitting, beginning at Exit 7 southbound, motorists can expect two daily rolling road blocks between the hours of 8:00am and 4:00pm causing approximately a 30-minute delay.

NARROW LANES – REDUCED SPEEDS – USE CAUTION!

Rockingham Bridges I-91

Written by on November 7, 2019 in Rockingham Bridges-I91
Rockingham Bridges I-91

The following is an update of the construction to take place for the week beginning Monday, November 11, 2019.

Southbound I-91 bridge activities:

Monday through Saturday:

  • Continue work on Pier 1 cap
  • Work continues on the southbound abutment (#1) approach
  • Weather permitting, continue girder erection
  • Continue maintenance of traffic control devises

Daily rolling roadblocks at approximately 8:00 a.m. and 4:00 p.m. for southbound motorists starting at Exit 7, expect approximately a 30-minute delay.

NARROW LANES – REDUCED SPEEDS – USE CAUTION!

Rockingham Bridges I-91

Written by on October 31, 2019 in Rockingham Bridges-I91

The following is an update of the construction to take place for the week beginning Monday, November 4, 2019.

Southbound I-91 bridge activities:

Monday through Saturday:

  • Continue work on placement of Pier 1 cap
  • Work continues on the southbound abutment (#1) approach
  • Weather permitting, begin girder erection
  • Continue maintenance of traffic control devises

Daily rolling roadblocks 7:00 a.m. and 4:00 p.m. for southbound motorists starting at Exit 7, expect approximately a 30-minute delay.

NARROW LANES – REDUCED SPEEDS – USE CAUTION!

Rockingham Bridges I-91

Written by on October 24, 2019 in Rockingham Bridges-I91
Rockingham Bridges I-91

The following is an update of the construction to take place for the week beginning Monday, October 28, 2019.

Southbound I-91 bridge activities:

Monday through Saturday:

  • Continue work on Pier 2
  • Place Pier 1 cap
  • Work continues on the southbound abutment (#1) approach
  • Work continues on the northbound abutment (#2) approach
  • Continue receiving girders onsite
  • Continue maintenance of traffic control devises

Wednesday through Friday:

  • Weather permitting, begin setting girders on Pier 3 utilizing the rolling roadblocks allowing to facilitate the girder erection. 
  • At approximately 7:00 a.m. and 4:00 p.m. starting at Exit 7, motorists can expect a rolling roadblock for approximately a 30-minute delay to allow for beam deliveries. These deliveries will be through Friday and continue the following Monday through Friday.

NARROW LANES – REDUCED SPEEDS – USE CAUTION!

Rockingham Bridges I-91

Written by on October 17, 2019 in Rockingham Bridges-I91

The following is an update of the construction to take place for the week beginning Monday, October 21, 2019.

Southbound I-91 bridge activities:

Monday through Saturday:

  • Continue work on Pier 2
  • Prep work for Pier 1 cap
  • Work continues on the southbound abutment (#1) approach
  • Continue receiving girders onsite
  • Continue maintenance of traffic control devises

I-91 SOUTHBOUND ROLLING ROADBLOCKS NOTIFICATION:

Beginning October 28, 2019, weather permitting at 7:00 a.m. and 12:30 p.m.  starting at Exit 7, motorists can expect a rolling roadblock for approximately a 30-minute delay to allow for beam deliveries. These deliveries will be Monday through Friday.

NARROW LANES – REDUCED SPEEDS – USE CAUTION!