Rockingham Bridges-I91

The Vermont Agency of Transportation in conjunction with the design/build team of Reed & Reed, Inc. will complete bridge replacement on the I-91 bridges #24S & 24N over the Williams River in Rockingham, VT. This project has an anticipated completion date of September 2021.

I-91 NORTHBOUND & SOUTHBOUND ARE REDUCED TO ONE LANE WITHIN THE CONSTRUCTION ZONE.


I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY! 

PLEASE USE CAUTION!


Anyone with questions or concerns regarding the project may contact Stephanie Barrett, Public Relations Officer at 802-862-6085 or toll free at 866-602-6868.

Follow us on Facebook    Follow us on Twitter (#91rockbridges)  Live Traffic Camera

Facebook Logo

Rockingham Bridges I-91

Written by on October 10, 2019 in Rockingham Bridges-I91

The following is the anticipated work schedule for the week beginning Tuesday, October 15, 2019

Southbound I-91 bridge activities:

Tuesday through Friday:

  • Continue work on Pier 2
  • Form work for placing shaft 2 at Pier 1
  • Breakdown of old Pier 1
  • Work continues at the northbound abutment (#2) approach
  • Work continues on the southbound abutment (#1) approach
  • Begin receiving girders onsite
  • Continue maintenance of traffic control devises.

I-91 SOUTHBOUND ROLLING ROADBLOCKS NOTIFICATION:

Beginning October 24, 2019, weather permitting at 7:00 a.m. and 12:30 p.m.  starting at Exit 7, motorists can expect a rolling roadblock for approximately a 30-minute delay to allow for beam deliveries. These deliveries will be Monday through Friday.

NARROW LANES – REDUCED SPEEDS – USE CAUTION!

Rockingham Bridges I-91

Written by on October 3, 2019 in Rockingham Bridges-I91

The following is the anticipated work schedule for the week beginning Saturday, October 5, 2019

Southbound I-91 bridge activities:

Saturday, Monday through Friday:

  • Continue work on Pier 2 for cap placement
  • Continue form work for placing shaft 1 at Pier 1
  • Work continues at the northbound abutment (#2) approach
  • Work continues on the southbound abutment (#1) approach
  • Continue maintenance of traffic control devises.

NARROW LANES – REDUCED SPEEDS – USE CAUTION!

Rockingham Bridges I-91

Written by on September 26, 2019 in Rockingham Bridges-I91

The following is the anticipated work schedule for the week beginning Saturday, September 28, 2019

Southbound I-91 bridge activities:

Saturday, Monday through Friday:

  • Continue work on Pier 2 for cap placement
  • Form work for placing shaft 1 at Pier 1
  • Work continues at the northbound abutment (#2) approach
  • Work continues on the southbound abutment (#1) approach
  • Complete demolition of the old southbound Piers
  • Continue maintenance of traffic control devises.

Rockingham Bridges I-91

Written by on September 19, 2019 in Rockingham Bridges-I91

The following is the anticipated work schedule for the week beginning Monday, September 23, 2019

Southbound I-91 bridge activities:

Monday through Friday:

  • Stripping Pier 3 cap forms
  • Continue work on Pier 2 for cap placement
  • Form work for placing Pier 1 footing
  • Work continues at the northbound abutment (#2) approach
  • Work continues on the southbound abutment (#1) approach
  • Continue demolition of the old southbound Pier 2
  • Continue maintenance of traffic control devises.

Rockingham Bridges I-91

Written by on September 12, 2019 in Rockingham Bridges-I91
Rockingham Bridges I-91

The following is the anticipated work schedule for the week beginning Saturday, September 14, 2019

Southbound I-91 bridge activities:

Saturday, Monday through Friday:

  • Continue forming and placing Pier 3 cap
  • Continue work on Pier 2 shaft
  • Work continues at the northbound abutment (#2) approach
  • Work continues on the southbound abutment (#1) approach
  • Continue demolition of the existing southbound Pier’s 2 and 3
  • Continue work at the new Pier 1
  • Continue maintenance of traffic control devises.

KEEP YOUR HEAD UP AND YOUR CELL PHONE DOWN!

Rockingham Bridges I-91

Written by on September 5, 2019 in Rockingham Bridges-I91

Below is the anticipated work schedule for the week beginning Monday, September 09, 2019:

Southbound I-91 bridge activities:

Monday through Friday:

  • Continue Pier 3 cap work
  • Continue work on Pier 2
  • Grading at northbound abutment (#2) approach and begin form work
  • Work continues on the southbound abutment (#2) approach
  • Continue demolition of the existing southbound Pier 3 causing late work activities
  • Continue work at the new Pier 1 site
  • Continue maintenance of traffic control devises.

KEEP YOUR HEAD UP AND YOUR CELL PHONE DOWN!

Rockingham Bridges I-91

Written by on August 29, 2019 in Rockingham Bridges-I91

Below is the anticipated work schedule for the week beginning Tuesday, September 03, 2019:

Southbound I-91 bridge activities:

Tuesday through Friday:

  • Continue Pier 3 cap forms
  • Form and place Pier 2 section 4
  • Work continues on each abutment approaches
  • Demolition of the existing southbound Pier 3
  • Continue work at the new Pier 1
  • Continue maintenance of traffic control devises.

KEEP YOUR HEAD UP AND YOUR CELL PHONE DOWN!

Rockingham Bridges I-91

Written by on August 22, 2019 in Rockingham Bridges-I91

Below is the anticipated work schedule for the week beginning Monday, August 26, 2019:

Southbound I-91 bridge activities:

Monday through Friday:

  • Begin Pier 3 cap forms
  • Begin Pier 2 shaft section 4
  • Work continues on each abutment approaches
  • Demolition of the existing southbound Pier 1
  • Begin shoring around the new Pier 1
  • Continue maintenance of traffic control devises.

KEEP YOUR HEAD UP AND YOUR CELL PHONE DOWN!

Rockingham Bridges I-91

Written by on August 15, 2019 in Rockingham Bridges-I91

Below is the anticipated work schedule for the week beginning Monday, August 19, 2019:

Southbound I-91 bridge activities:

Monday through Friday:

  • Continue Pier 3 shaft section 4
  • Continue Pier 2 shaft section 3
  • Work continues on each abutment approaches
  • Demolition of the existing southbound Pier 1
  • Begin work on building the new Pier 1
  • Continue maintenance of traffic control devises.

KEEP YOUR HEAD UP AND YOUR CELL PHONE DOWN!

Rockingham Bridges I-91

Written by on August 8, 2019 in Rockingham Bridges-I91

Below is the anticipated work schedule for the week beginning Monday, August 12, 2019:

Southbound I-91 bridge activities:

Monday through Friday:

  • Continue substructure removal
  • Continue Pier 3 shaft section 4
  • Continue Pier 2 shaft section 3
  • Work continues on each abutment approaches
  • Demolition of the existing southbound Pier 1
  • Continue maintenance of traffic control devises.

KEEP YOUR HEAD UP AND YOUR CELL PHONE DOWN!