Rockingham Bridges-I91
The Vermont Agency of Transportation in conjunction with the design/build team of Reed & Reed, Inc. will complete bridge replacement on the I-91 bridges #24S & 24N over the Williams River in Rockingham, VT. This project has an anticipated completion date of September 2021.
I-91 NORTHBOUND & SOUTHBOUND ARE REDUCED TO ONE LANE WITHIN THE CONSTRUCTION ZONE.
I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY!
PLEASE USE CAUTION!
Anyone with questions or concerns regarding the project may contact Stephanie Barrett, Public Relations Officer at 802-862-6085 or toll free at 866-602-6868.
Follow us on Facebook Follow us on Twitter (#91rockbridges) Live Traffic Camera
Below is the anticipated work schedule for the week beginning Monday, August 5, 2019:
Southbound I-91 bridge activities:
Monday through Friday:
- Nighttime activity is done until further notice
- Continue substructure removal
- Continue placing Pier 3 shaft section 3
- Continue Pier 2 shaft work
- Grade work on the northbound abutment
- Demolition of the southbound abutment
- Continue maintenance of traffic control devises.
KEEP YOUR HEAD UP AND YOUR CELL PHONE DOWN!
Below is the anticipated work schedule for the week beginning Monday, July 28, 2019:
Monday through Friday (24-hour days) :
- Continue removal of the existing southbound bridge to include floor beams
- Continue substructure removal
- Continue maintenance of traffic control devises.
KEEP YOUR HEAD UP AND YOUR CELL PHONE DOWN!
Below is the anticipated work schedule for the week beginning Monday, July 22, 2019:
Monday through Friday (24-hour days) :
- Continue removal of the existing southbound bridge to include floor beams
- Continue substructure removal
- Preparation for new install of Pier 3
- Continue maintenance of traffic control devises.
KEEP YOUR HEAD UP AND YOUR CELL PHONE DOWN!
Below is the anticipated work schedule for the week beginning Monday, July 15, 2019:
Monday through Friday (24-hour days) :
- Continue removal of the existing southbound bridge to include floor beams
- Begin substructure removal
- Continue maintenance of traffic control devises.
KEEP YOUR HEAD UP AND YOUR CELL PHONE DOWN!
Below is the anticipated work schedule for the week beginning Monday, June 17, 2019:
Monday thru Friday:
- Continue removal of bridge rail and curb
- Continue removal of the existing southbound bridge deck
- Work continues on SB Piers #2 & #3.
NOTE: New summer hours begins this week with double shifts as follows:
- Monday: 7am to 6pm
- Tuesday thru Thursday: 6am to 6pm
- Friday: 6am to noon
- Monday thru Thursday: 6pm to 6am
KEEP YOUR HEADS UP AND YOUR CELL PHONE DOWN!
*** EXIT 6 SOUTHBOUND OFF-RAMP ***
Due to the weather conditions this week causing delays in the line striping, the Exit 6 southbound off-ramp will not re-open at the end of the workday today. Motorists can expect it to be open by noon time tomorrow Friday, June 07, 2019.
We apologize in advance for any inconvenience this may cause.
Below is the anticipated work schedule for the week beginning Monday, June 10, 2019:
** The new northbound bridge is now open to southbound motorists **
Monday thru Friday:
- Begin removal of bridge rail
- Continue removal of the existing southbound bridge deck
- Work continues on SB Piers #2 & #3
- Continue installation of the southbound traffic control devises
KEEP YOUR HEADS UP AND YOUR CELL PHONE DOWN!