For the work schedule for the week beginning Saturday, August 4, 2018:
Saturday, Monday thru Friday:
• Continued removal of unsuitable material and backfilling with new material to proper grade from N. Williston Road proceeding westbound to Tiffany Lane.
• Continued slope stabilization work between Skunk Hollow & Barber Farm Roads.
Monday thru Wednesday:
• Excavation work continues from VT-289 off ramp to Tiffany Lane.
Thursday & Friday:
• Culvert replacement continues between N. Williston Road and the Essex/Jericho Town line.
ROADWAY MAINTENANCE THROUGHOUT THE PROJECT!
MOTORISTS PLEASE BE AWARE:
There will not be a center line from the Essex/Jericho Town line to Tiffany Lane
Rough roadway surface
Please drive slowly & use caution!
Commuting motorists should seek alternate routes. Expect delays during peak hours!