Next week’s anticipated schedule on VT 117:

Written by on August 10, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

For the week beginning Saturday, August 11, 2018:

 Saturday:

  • Grading the roadway between VT-289 and Tiffany Lane.

 Monday & Tuesday:

  • Grading continues between Sand Hill Road and the Essex/Jericho Town line.
  • Culvert replacement work continues near N. Williston Road.

Wednesday thru Friday:

  • 2nd reclaiming phase to begin which includes adding a stabilize agent to the subbase. This agent takes time to cure causing a maximum of 2 hour lane restriction after installation is completed.

 

Motorists please be aware:

  • There will not be a center line from the Essex/Jericho Town line to Tiffany Lane
  • Rough roadway surface
  • Please drive slowly & use caution!

 

Commuting motorists should seek alternate routes.  Expect delays during peak hours!