For the week beginning Saturday, August 11, 2018:
Saturday:
- Grading the roadway between VT-289 and Tiffany Lane.
Monday & Tuesday:
- Grading continues between Sand Hill Road and the Essex/Jericho Town line.
- Culvert replacement work continues near N. Williston Road.
Wednesday thru Friday:
- 2nd reclaiming phase to begin which includes adding a stabilize agent to the subbase. This agent takes time to cure causing a maximum of 2 hour lane restriction after installation is completed.
Motorists please be aware:
- There will not be a center line from the Essex/Jericho Town line to Tiffany Lane
- Rough roadway surface
- Please drive slowly & use caution!
Commuting motorists should seek alternate routes. Expect delays during peak hours!