For the week beginning Saturday, August 18, 2018:
Saturday:
- 7:00 am Weather permitting, continue 2nd reclaiming phase from approximately N. Williston Road proceeding west through the Sand Hill Road intersection.
Monday thru Friday:
- Weather permitting, continue 2nd reclaiming phase working westbound to Tiffany Lane, Essex.
- Slope stabilization work continues between Barber Farm Road and the US Route 2 intersection, Richmond.
- Culvert replacement just west of the Barber Farm Road intersection.
- Underdrain work continues between Barber Farm Road and US Route 2 intersection.
Motorists please be aware:
- There will not be a center line from the Essex/Jericho Town line to Tiffany Lane
- Rough roadway surface
- Please drive slowly & use caution!
Commuting motorists should seek alternate routes. Expect delays during peak hours!
Traffic control will be present allowing for one lane of alternating traffic within the construction areas.