Next week’s anticipated schedule on VT 117:

Written by on August 16, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

For the week beginning Saturday, August 18, 2018:

 Saturday:

  • 7:00 am Weather permitting, continue 2nd reclaiming phase from approximately N. Williston Road proceeding west through the Sand Hill Road intersection.

Monday thru Friday:

  • Weather permitting, continue 2nd reclaiming phase working westbound to Tiffany Lane, Essex.
  • Slope stabilization work continues between Barber Farm Road and the US Route 2 intersection, Richmond.
  • Culvert replacement just west of the Barber Farm Road intersection.
  • Underdrain work continues between Barber Farm Road and US Route 2 intersection.

 

Motorists please be aware:

  • There will not be a center line from the Essex/Jericho Town line to Tiffany Lane
  • Rough roadway surface
  • Please drive slowly & use caution!  

Commuting motorists should seek alternate routes.  Expect delays during peak hours!

Traffic control will be present allowing for one lane of alternating traffic within the construction areas.