The following is the anticipated work schedule for the week beginning Monday, October 01, 2018.
 
I-91 northbound bridge activities:
Monday thru Thursday – 5:00pm to 5:00am
Monday thru Friday – Daytime:
• Continue installation of bridge deck prep and overhang.
• Remove back wall forms at the northern abutment.
• Continue forming back wall at the southern abutment.
 
Please drive slow & use caution thru the work zone.