The following is an update of the construction to take place for the week beginning Monday, February 8, 2021.
Monday through Friday – 6:00 a.m. to 5:00 p.m.:
- Bridge barrier work continues. Motorists should be aware of trucks entering/exiting the construction zone.
- Backfilling around the pier bases continues
- Maintenance of traffic control devices continues
NARROW LANES – REDUCED SPEEDS – USE CAUTION!