The following is the anticipated work schedule on the I-91 bridges for the week beginning Monday, January 26, 2019:
Monday thru Friday:
- Continue installation of the southbound Pier #3 cofferdam
- Continue stripping northbound deck overhang form work
- Begin drilling ledge for installation of southbound Pier #2 cofferdam
- Begin installation of retaining wall at southbound Pier #2
- Continue maintenance of traffic control devices, due to weather
I-91 NORTHBOUND & SOUTHBOUND IS REDUCED TO ONE LANE WITH NO SHOULDERS WITHIN THE CONSTRUCTION ZONE.
I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY!
PLEASE USE CAUTION!