The following is the anticipated work schedule on the I-91 bridges for the week beginning Monday, February 11, 2019:
Monday thru Friday:
- Continue installation of retaining pike for the southbound Pier #3 cofferdam
- Installation of hangers and conduit under the NB Bridge
- Continue drilling ledge for installation of southbound Pier #2 cofferdam
- Continue installation of wind stops on NB Bridge
- Continue maintenance of traffic control devices, due to weather
I-91 NORTHBOUND & SOUTHBOUND IS REDUCED TO ONE LANE WITH NO SHOULDERS WITHIN THE CONSTRUCTION ZONE.
I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY!
PLEASE USE CAUTION!