The following is the anticipated work schedule on the I-91 bridges for the week beginning Monday, February 18, 2019:

Monday thru Friday:

  • Excavate for the southbound Pier #3 cofferdam
  • Continue installation of conduit under the NB Bridge
  • Continue drilling ledge for installation of southbound Pier #2 cofferdam
  • Excavate at Pier #2 cofferdam to prep for sheet pile installation
  • Continue maintenance of traffic control devices, due to weather

I-91 NORTHBOUND & SOUTHBOUND IS REDUCED TO ONE LANE WITH NO SHOULDERS WITHIN THE CONSTRUCTION ZONE. 

I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY!
PLEASE USE CAUTION!