The following is the anticipated work schedule on the I-91 bridges for the week beginning Monday, April 01, 2019:

********************* IMPORTANT NOTIFICATION *********************

On Monday, April 15, 2019 at 7 a.m. we will be closing the I-91 Exit 6 northbound On-Ramp for two weeks while the ramp is reconstructed to its original grade.  All motorists will follow a signed detoured on Route 5 north to the Exit 7 northbound On-Ramp.  The ramp is anticipated to be opened up on April 26, 2019 at which time all traffic will be switched over to the new I-91 Northbound Bridge.

************************************************************************

Monday thru Friday

  • Continue form work for Pier #3 southbound footing
  • Continue to excavate and remove ledge at Pier #2 SB cofferdam
  • Continue various items for the completion of the NB Bridge to include the installation of the deck membrane and concrete curb on the bridge corners
  • Continue maintenance of traffic control devices, due to weather

I-91 NORTHBOUND & SOUTHBOUND IS REDUCED TO ONE LANE WITH NO SHOULDERS WITHIN THE CONSTRUCTION ZONE. 

I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY!
PLEASE USE CAUTION!