The following is the anticipated work schedule on the I-91 bridges for the week beginning Monday, April 08, 2019:
IMPORTANT NOTIFICATION
On Monday, April 15, 2019 at 7 a.m. we will be closing the I-91 Exit 6 northbound On-Ramp for two weeks while the ramp is reconstructed to its original grade. All motorists will follow a signed detoured on Route 5 north to the Exit 7 northbound On-Ramp. The ramp is anticipated to be opened up on April 26, 2019 at which time all traffic will be switched over to the new I-91 Northbound Bridge.
************************************************************************
Monday thru Friday:
- Preparation work for placement of concrete at Pier #3 southbound
- Continue to excavate and remove ledge at Pier #2 SB cofferdam
- Grinding and fine grading of the NB Bridge approaches
- Continue installation of concrete curb on the bridge corners
- Continue maintenance of traffic control devices, due to weather
I-91 NORTHBOUND & SOUTHBOUND IS REDUCED TO ONE LANE WITH NO SHOULDERS WITHIN THE CONSTRUCTION ZONE.
I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY!
PLEASE USE CAUTION!