The following is the anticipated work schedule on the I-91 bridges for the week beginning Monday, April 15, 2019:
IMPORTANT NOTIFICATION
Monday thru Friday:
- 7 a.m. I-91 Exit 6 northbound On-Ramp will be closed for two weeks while the ramp is reconstructed to its original grade. All motorists will follow a signed detoured on Route 5 north to the Exit 7 northbound On-Ramp. The ramp is anticipated to be opened up on April 26, 2019 at which time all traffic will be switched over to the new I-91 Northbound Bridge.
- Fine grading of the NB Bridge approaches
- Grinding and fine grading of the NB Bridge approaches
- Weather permitting, paving the NB Bridge and approaches
- Continue to excavate and remove ledge at Pier #2 SB cofferdam
I-91 NORTHBOUND & SOUTHBOUND IS REDUCED TO ONE LANE WITH NO SHOULDERS WITHIN THE CONSTRUCTION ZONE.
I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY!
PLEASE USE CAUTION!