The following is the anticipated work schedule on the I-91 bridges for the week beginning Monday, April 22, 2019:
Monday thru Friday:
- I-91 Exit 6 northbound On-Ramp remains closed for the week during ramp reconstruction to its original grade. All motorists to follow the signed detoured on Route 5 north to the Exit 7 northbound On-Ramp. The ramp is anticipated to be opened up on April 26, 2019 at which time all traffic will be switched over to the new I-91 Northbound Bridge.
- Weather permitting, paving the NB Bridge approaches
- Guardrail installation on the NB Bridge approaches
- Pavement markings on the NB Bridge and approaches
- Installation of new NB traffic control devices
- Work continues on Pier #3 to include placement of 2nd shaft
- Continue to excavate and remove ledge at Pier #2 SB cofferdam
Friday – April 26, 2019:
- Weather permitting, there will be a northbound rolling road block as motorists are directed over the newly constructed northbound bridge. Motorists can anticipate approximately a 10-minute delay in their travels. The start of the road block will be listed in next week’s release.
I-91 NORTHBOUND & SOUTHBOUND IS REDUCED TO ONE LANE WITH NO SHOULDERS WITHIN THE CONSTRUCTION ZONE.
I-91 NORTHBOUND MOTORISTS SHOULD BE AWARE OF MERGING RAMP TRAFFIC ENTERING THE ROADWAY!
PLEASE USE CAUTION!