The following is the anticipated work schedule on the I-91 bridges for the week beginning Monday, April 29, 2019:
Monday thru Friday:
- Work begins on building the crossover to re-route all traffic onto the NB Bridge
- Work continues on SB Pier #3 to include placement of 2nd shaft
- Prep work for 1st placement of concrete at SB Pier #2
NARROW LANES – USE CAUTION!