Below is the anticipated work schedule for the week beginning Monday, May 27, 2019:
Monday:
No work due to the Memorial Day Holiday!
Tuesday thru Friday:
- Work continues on the installation of the southbound crossover to include paving, shoulders & line striping.
- Work continues on SB Piers #2 & #3.
- Prep work on the existing southbound bridge for start of demolition
- Installation of the southbound traffic control devises.
REMINDERS:
- JUNE 04, 2019 at 9:30am there will be a rolling roadblock for southbound motorists in preparation of opening the southbound crossover. Motorists can anticipate approximately a 20-minute delay in their travels. If time does not allow for all work to be completed within the 20 minutes, there will be another rolling roadblock at 11:00am for approximately another 20-minute delay.
- JUNE 4, 2019 THRU JUNE 6, 2019 the EXIT 6 SOUTHBOUND OFF-RAMP WILL BE CLOSED AT 9:30am June 4, 2019 until the end of the workday June 6, 2019. Motorists will be detoured using Exit 7 Off-Ramp then follow the signed detour on Route 5 southbound. All trucks over 14’ high will follow a signed detoured using Route 11.
KEEP YOUR HEADS UP AND YOUR CELL PHONE DOWN!