Rockingham Bridges I-91

Written by on October 18, 2018 in Rockingham Bridges-I91

The following is the anticipated work schedule for the week beginning Monday, October 22, 2018:

I-91 northbound bridge activities:

Monday thru Thursday – 5:00pm to 5:00am
Monday thru Friday – Daytime:

• Complete placing concrete deck segments.
• Complete approach road work up to the approach slab area.
• Continue work on approaches.
• Continue placement of the barrier curb.

Please use caution while traveling thru the work zone.