The following is an update of the construction to take place for the week beginning Monday, April 5, 2021.
Monday through Friday – 6:00 a.m. to 5:00 p.m.:
- Bridge barrier work continues. Motorists should be aware of trucks entering/exiting the construction zone
- Continue backfilling and slope adjustment around both the northbound & southbound pier bases
- Partial removal of work trestle
- Maintenance of traffic control devices continues
NARROW LANES – REDUCED SPEEDS – USE CAUTION!