Below is the anticipated work schedule for the week beginning Monday, July 28, 2019:
Monday through Friday (24-hour days) :
- Continue removal of the existing southbound bridge to include floor beams
- Continue substructure removal
- Continue maintenance of traffic control devises.
KEEP YOUR HEAD UP AND YOUR CELL PHONE DOWN!