Below is the anticipated work schedule for the week beginning Monday, August 12, 2019:
Southbound I-91 bridge activities:
Monday through Friday:
- Continue substructure removal
- Continue Pier 3 shaft section 4
- Continue Pier 2 shaft section 3
- Work continues on each abutment approaches
- Demolition of the existing southbound Pier 1
- Continue maintenance of traffic control devises.
KEEP YOUR HEAD UP AND YOUR CELL PHONE DOWN!
Connect