Below is the anticipated work schedule for the week beginning Monday, August 12, 2019:

Southbound I-91 bridge activities:

Monday through Friday:

  • Continue substructure removal
  • Continue Pier 3 shaft section 4
  • Continue Pier 2 shaft section 3
  • Work continues on each abutment approaches
  • Demolition of the existing southbound Pier 1
  • Continue maintenance of traffic control devises.