Rockingham Bridges I-91

Written by on August 22, 2019 in Rockingham Bridges-I91

Below is the anticipated work schedule for the week beginning Monday, August 26, 2019:

Southbound I-91 bridge activities:

Monday through Friday:

  • Begin Pier 3 cap forms
  • Begin Pier 2 shaft section 4
  • Work continues on each abutment approaches
  • Demolition of the existing southbound Pier 1
  • Begin shoring around the new Pier 1
  • Continue maintenance of traffic control devises.