The following is the anticipated work schedule for the week beginning Monday, October 29, 2018:
I-91 northbound bridge activities:
Monday thru Thursday – 5:00pm to 5:00am
Monday thru Friday – Daytime:
- Continue work on both approaches.
- Continue curing of the concrete deck placements.
- Continue placement of the barrier curb.
Please use caution while traveling thru the work zone.