Written by on September 12, 2019 in Rockingham Bridges-I91

The following is the anticipated work schedule for the week beginning Saturday, September 14, 2019

Southbound I-91 bridge activities:

Saturday, Monday through Friday:

  • Continue forming and placing Pier 3 cap
  • Continue work on Pier 2 shaft
  • Work continues at the northbound abutment (#2) approach
  • Work continues on the southbound abutment (#1) approach
  • Continue demolition of the existing southbound Pier’s 2 and 3
  • Continue work at the new Pier 1
  • Continue maintenance of traffic control devises.