The following is the anticipated work schedule for the week beginning Monday, September 23, 2019

Southbound I-91 bridge activities:

Monday through Friday:

  • Stripping Pier 3 cap forms
  • Continue work on Pier 2 for cap placement
  • Form work for placing Pier 1 footing
  • Work continues at the northbound abutment (#2) approach
  • Work continues on the southbound abutment (#1) approach
  • Continue demolition of the old southbound Pier 2
  • Continue maintenance of traffic control devises.