The following is the anticipated work schedule for the week beginning Saturday, October 5, 2019
Southbound I-91 bridge activities:
Saturday, Monday through Friday:
- Continue work on Pier 2 for cap placement
- Continue form work for placing shaft 1 at Pier 1
- Work continues at the northbound abutment (#2) approach
- Work continues on the southbound abutment (#1) approach
- Continue maintenance of traffic control devises.
NARROW LANES – REDUCED SPEEDS – USE CAUTION!