The following is the anticipated work schedule for the week beginning Tuesday, October 15, 2019

Southbound I-91 bridge activities:

Tuesday through Friday:

  • Continue work on Pier 2
  • Form work for placing shaft 2 at Pier 1
  • Breakdown of old Pier 1
  • Work continues at the northbound abutment (#2) approach
  • Work continues on the southbound abutment (#1) approach
  • Begin receiving girders onsite
  • Continue maintenance of traffic control devises.

I-91 SOUTHBOUND ROLLING ROADBLOCKS NOTIFICATION:

Beginning October 24, 2019, weather permitting at 7:00 a.m. and 12:30 p.m.  starting at Exit 7, motorists can expect a rolling roadblock for approximately a 30-minute delay to allow for beam deliveries. These deliveries will be Monday through Friday.

NARROW LANES – REDUCED SPEEDS – USE CAUTION!