The following is an update of the construction to take place for the week beginning Monday, October 28, 2019.

Southbound I-91 bridge activities:

Monday through Saturday:

  • Continue work on Pier 2
  • Place Pier 1 cap
  • Work continues on the southbound abutment (#1) approach
  • Work continues on the northbound abutment (#2) approach
  • Continue receiving girders onsite
  • Continue maintenance of traffic control devises

Wednesday through Friday:

  • Weather permitting, begin setting girders on Pier 3 utilizing the rolling roadblocks allowing to facilitate the girder erection. 
  • At approximately 7:00 a.m. and 4:00 p.m. starting at Exit 7, motorists can expect a rolling roadblock for approximately a 30-minute delay to allow for beam deliveries. These deliveries will be through Friday and continue the following Monday through Friday.

NARROW LANES – REDUCED SPEEDS – USE CAUTION!