The following is an update of the construction to take place for the week beginning Monday, October 28, 2019.
Southbound I-91 bridge activities:
Monday through Saturday:
- Continue work on Pier 2
- Place Pier 1 cap
- Work continues on the southbound abutment (#1) approach
- Work continues on the northbound abutment (#2) approach
- Continue receiving girders onsite
- Continue maintenance of traffic control devises
Wednesday through Friday:
- Weather permitting, begin setting girders on Pier 3 utilizing the rolling roadblocks allowing to facilitate the girder erection.
- At approximately 7:00 a.m. and 4:00 p.m. starting at Exit 7, motorists can expect a rolling roadblock for approximately a 30-minute delay to allow for beam deliveries. These deliveries will be through Friday and continue the following Monday through Friday.
NARROW LANES – REDUCED SPEEDS – USE CAUTION!