The following is an update of the construction to take place for the week beginning Monday, November 11, 2019.
Southbound I-91 bridge activities:
Monday through Saturday:
- Continue work on Pier 1 cap
- Work continues on the southbound abutment (#1) approach
- Weather permitting, continue girder erection
- Continue maintenance of traffic control devises
Daily rolling roadblocks at approximately 8:00 a.m. and 4:00 p.m. for southbound motorists starting at Exit 7, expect approximately a 30-minute delay.
NARROW LANES – REDUCED SPEEDS – USE CAUTION!
Connect